Field Conditions. A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical. C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
Appears in 1 contract
Sources: Contract for Repairs, Maintenance or Small Construction Projects
Field Conditions. A. Owner will may occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practicalaspractical.
C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
Appears in 1 contract
Sources: Maintenance/Service Master Contract