Common use of Extensions of Deadlines Clause in Contracts

Extensions of Deadlines. The Contractor may request an extension of the deadline, which extension must have the written approval of the Customer in order to apply. The Customer shall not be entitled to claim liquidated damages, ordinary damages or other remedies for breach of contract in respect of the period comprised by an extension of the deadline. An extension of the deadline shall have no impact on the entitlement of the Customer to any liquidated damages or ordinary damages that accrue prior to the extension of the deadline.

Appears in 6 contracts