Common use of Extended COD Delays Clause in Contracts

Extended COD Delays. If the Commercial Operations Date for a Unit has not occurred on or before the date that is 120 days after the Target COD (as extended day-for-day for a Force Majeure Event) (the "Four Month Date"), then the applicable Capacity Rate shall be reduced (the "Capacity Rate Reduction") by an amount equal to $.01 KW-month multiplied by a fraction, the numerator of which is the number of days from the Four Month Date to the Commercial Operations Date and the denominator of which is thirty (30) days. The Capacity Rate Reduction shall take effect beginning with the later to occur of (i) June 1 of the second Contract Year and (ii) the Commercial Operations Date, and continue for the remainder of the Term.

Appears in 2 contracts

Samples: Power Sales Agreement (Aquila Inc), Power Sales Agreement (Aquila Inc)

AutoNDA by SimpleDocs

Extended COD Delays. If the Commercial Operations Date ------------------- for a Unit has not occurred on or before the date that is 120 days after the Target COD (as extended day-for-day for a Force Majeure Event) (the "Four Month Date"), then the applicable Capacity Rate shall be reduced (the "Capacity Rate Reduction") by an amount equal to $.01 KW-month multiplied by a fraction, the numerator of which is the number of days from the Four Month Date to the Commercial Operations Date and the denominator of which is thirty (30) days. The Capacity Rate Reduction shall take effect beginning with the later to occur of (i) June 1 of the second Contract Year and (ii) the Commercial Operations Date, and continue for the remainder of the Term.

Appears in 1 contract

Samples: Power Sales Agreement (Dominion Resources Inc /Va/)

AutoNDA by SimpleDocs

Extended COD Delays. If the Commercial Operations Date for ------------------- a Unit has not occurred on or before the date that is 120 days after the Target COD (as extended day-for-day for a Force Majeure Event) (the "Four Month Date"), then the applicable Capacity Rate shall be reduced (the "Capacity Rate Reduction") by an amount equal to $.01 KW-month multiplied by a fraction, the numerator of which is the number of days from the Four Month Date to the Commercial Operations Date and the denominator of which is thirty (30) days. The Capacity Rate Reduction shall take effect beginning with the later to occur of (i) June 1 of the second Contract Year and (ii) the Commercial Operations Date, and continue for the remainder of the Term.

Appears in 1 contract

Samples: Power Sales Agreement (Dominion Resources Inc /Va/)