Execution of Change Orders. Change Orders shall be signed by the Contractor, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 below.
Appears in 59 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Execution of Change Orders. Change Orders shall be signed by the ContractorCM/GC, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor CM/GC for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 3.4.7.3 below.
Appears in 3 contracts
Samples: Construction Management Contract, Construction Management Contract, Construction Management Contract
Execution of Change Orders. Change Orders shall be signed by the ContractorDesign-Builder, ordinarily certified by the Design ProfessionalExecutive Administrator, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor Design-Builder for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article Section 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 3.4.7.3 below.
Appears in 2 contracts
Samples: gsfic.georgia.gov, Construction Contract
Execution of Change Orders. Change Orders shall be signed by the Contractor, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 below. Disagreement between Design Professional and Contractor.
Appears in 1 contract
Samples: ssl.doas.state.ga.us
Execution of Change Orders. Change Orders shall be signed by the ContractorDesign-Builder, ordinarily certified by the Design ProfessionalProgram Manager, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor Design-Builder for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph 3.2.7.3 3.4.7.3 below.
Appears in 1 contract
Samples: Design Build Contract
Execution of Change Orders. Change Orders shall be signed by the Contractor, ordinarily certified by the Design Professional, and approved by the Owner in accordance with the form of Change Order prescribed by the Owner. No request for payment by the Contractor for a Change Order shall be due, nor shall any such request appear on an Application for Payment, until the Change Order is executed by the Owner. In the event of emergency (see Article 1.4.4) or significant impact to the Overall Project Schedule, the Owner shall direct the Change Order to proceed upon a Force Account until the cost and time is resolved in the manner set forth in Paragraph Article 3.2.7.3 below.
Appears in 1 contract
Samples: Construction Contract