Common use of Eighty Percent Notification Clause in Contracts

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task Order; or (2) where the total anticipated cost for performance of the Scope of Services may be greater than the maximum compensation for this Agreement or for any Task Order.

Appears in 11 contracts

Samples: Original, Agreement, Agreement

AutoNDA by SimpleDocs

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services [Exhibit A] appears that it may be greater than the maximum compensation for this Agreement or for any Task OrderAgreement.

Appears in 9 contracts

Samples: Agreement, Agreement, Agreement

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task Order; or (2) where the total anticipated cost for performance of the Scope of Services may be greater than the maximum compensation for this Agreement or for any Task Order.Order.‌

Appears in 5 contracts

Samples: Agreement, Agreement, www.sandiego.gov

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services (Exhibit A) appears that it may be greater than the maximum compensation for this Agreement or for any Task OrderAgreement.

Appears in 4 contracts

Samples: Agreement, Agreement, Agreement

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services (Exhibit A) appears that it may be greater than the maximum compensation for this Agreement or for any Task Order.Agreement.‌

Appears in 2 contracts

Samples: Agreement, Agreement

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderTask; or (2) where the total anticipated cost for performance of the Scope of Services appears that it may be greater or less than the maximum compensation for this Agreement or for any Task OrderTask.

Appears in 2 contracts

Samples: Agreement, dockets.sandiego.gov

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 So percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services (Exhibit A) appears that it may be greater than the maximum compensation for this Agreement or for any Task OrderAgreement.

Appears in 1 contract

Samples: faast.waterboards.ca.gov

AutoNDA by SimpleDocs

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services [Exhibit A] appears that it may be greater than the maximum compensation for this Agreement or for any Task Order.Agreement.‌ ARTICLE IV‌‌‌

Appears in 1 contract

Samples: Agreement

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services (Exhibit A) appears that it may be greater than the maximum compensation for this Agreement or for any Task Order.Agreement. ARTICLE IV‌‌

Appears in 1 contract

Samples: www.sandiego.gov

Eighty Percent Notification. The Design Professional shall promptly notify the City in writing of any potential cost overruns. Cost overruns include, but are not limited to the following: (1) where anticipated costs to be incurred in the next sixty calendar days, when added to all costs previously incurred, will exceed 80 percent of the maximum compensation for this Agreement or for any issued Task OrderAgreement; or (2) where the total anticipated cost for performance of the Scope of Services (Exhibit A) appears that it may be greater than the maximum compensation for this Agreement or for any Task Order.Agreement.‌ ARTICLE IV‌‌‌

Appears in 1 contract

Samples: Design Professional Services