Document Management. 7.7.3.1. The RPR shall be responsible for submittal management as described in Section 7.3. The RPR shall perform an initial review of the submittals and electronically send the submittals to the EOR and/or NBU for a detailed review and response. 7.7.3.2. The RPR shall monitor the progress of (i) the contractor in sending and processing submittals, including obtaining signatures from all required parties for documents, and of (ii) the EOR in reviewing and responding to submittals. The RPR shall verify that documentation is being processed according to the schedule. 7.7.3.3. The RPR shall prepare monthly reports that monitor the status of all submittals in the review process. The RPR shall submit an electronic copy of the report to NBU once a month.
Appears in 2 contracts
Sources: Professional Services, Professional Services
Document Management. 7.7.3.1. i) The RPR shall be responsible for submittal management as described in Section 7.3Submittal Management. The RPR shall perform an initial review of the submittals and electronically send the submittals to the EOR and/or the NBU Project Manager for a detailed review and response.
7.7.3.2. ii) The RPR shall monitor the progress of (i) the contractor in sending and processing submittals, including obtaining signatures from all required parties for documents, and of (ii) the EOR in reviewing and responding to submittals. The RPR shall verify that documentation processed is being processed according to the schedule.
7.7.3.3. iii) The RPR shall prepare monthly reports that monitor the status of all submittals in the review process. The RPR shall submit an electronic copy of the report to the NBU Project Manager once a monthmonth via email.
Appears in 1 contract
Sources: Professional Services
Document Management. 7.7.3.1. The RPR shall be responsible for submittal management as described in Section 7.3. The RPR shall perform an initial review of the submittals and electronically send the submittals to the EOR and/or the NBU Project Manager for a detailed review and response.
7.7.3.2. The RPR shall monitor the progress of (i) the contractor in sending and processing submittals, including obtaining signatures from all required parties for documents, and of (ii) the EOR in reviewing and responding to submittals. The RPR shall verify that documentation is being processed according to the schedule.
7.7.3.3. The RPR shall prepare monthly reports that monitor the status of all submittals in the review process. The RPR shall submit an electronic copy of the report to NBU once a month.
Appears in 1 contract
Sources: Professional Services
Document Management. 7.7.3.1. The RPR shall be responsible for submittal management as described in Section 7.3. The RPR shall perform an initial review of the submittals and electronically send the submittals to the EOR and/or NBU for a detailed review and response.
7.7.3.2. The RPR shall monitor the progress of (i) the contractor in sending and processing submittals, including obtaining signatures from all required parties for documents, and of (ii) the EOR in reviewing and responding to submittals. The RPR shall verify that documentation is being processed according to the schedule.
7.7.3.3. The RPR shall prepare monthly reports in accordance with Section 7.7.1.4 that monitor the status of all submittals in the review process. The RPR shall submit an electronic copy of the report to NBU once a month.
Appears in 1 contract
Sources: Professional Services