Common use of Delayed authorisation Clause in Contracts

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof all items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 7 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a beyonda period of 60 (sixty) days from the date of completionof completion of all safety/critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and & commissioning as specified in Schedule-G.

Appears in 5 contracts

Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof all items issue of punch listthe Provisional Certificate, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percentper cent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 4 contracts

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Standard Engineering, Procurement and Construction (Epc) Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety/critical items of the punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Epc Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety / critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Engineering, Procurement and Construction (Epc) Agreement

Delayed authorisation. 12.6.1 In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety / critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Epc Agreement

Delayed authorisation. 12.6.1 In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completion of all safety / critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percentper cent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Epc Agreement

Delayed authorisation. In the event of delay in issuance of authorisation by the Commissioner of Railway Safety beyond a period of 60 (sixty) days from the date of completionof completioion of all safety/critical items of punch list, the Contractor shall be entitled to interest for the period of delay at a rate equal to 3% (three percent) above the Bank Rate on the payment due for integrated testing and commissioning as specified in Schedule-G.

Appears in 1 contract

Sources: Engineering, Procurement and Construction (Epc) Agreement