Procedure for Change of Scope Sample Clauses

Procedure for Change of Scope. 16.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated thereunder (the “Change of Scope Notice”).
AutoNDA by SimpleDocs
Procedure for Change of Scope. (i) In the event of the Authority determining that a Change of Scope is necessary, it may direct the Authority’s Engineer to issue to the Contractor a notice specifying in reasonable detail the Works and services contemplated thereunder (the “Change of Scope Notice”). The Contractor shall submit a detailed proposal as per Clause 13.2 (iii) within 15 days from the receipt of Change of Scope Notice.
Procedure for Change of Scope. In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated thereunder (the “Change of Scope Notice”). Upon receipt of a Change of Scope Notice, the Concessionaire shall, with due diligence, provide to the Authority such information as is necessary, together with preliminary Documentation in support of: the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including a detailed breakdown by work classifications specifying the material and labour costs calculated in accordance with the schedule of rates applicable to the works assigned by the Authority to its contractors, along with the proposed premium/discount on such rates; provided that the cost incurred by the Concessionaire in providing such information shall be reimbursed by the Authority to the extent such cost is certified by the Independent Engineer as reasonable. Upon receipt of information set forth in Clause 16.2.2, if the Authority decides to proceed with the Change of Scope, it shall convey its preferred option to the Concessionaire, and the Parties shall, with assistance of the Independent Engineer, thereupon make good faith efforts to agree upon the time and costs for implementation thereof. Upon reaching an agreement, the Authority shall issue an order (the “Change of Scope Order”) requiring the Concessionaire to proceed with the performance thereof. In the event that the Parties are unable to agree, the Authority may, by issuing a Change of Scope Order, require the Concessionaire to proceed with the performance thereof pending resolution of the Dispute, or carry out the works in accordance with Clause 16.5. The provisions of this Agreement, insofar as they relate to Construction Works and Tests, shall apply mutatis mutandis to the works undertaken by the Concessionaire under this Article 16.
Procedure for Change of Scope. If either Party proposes a Change of Scope, then the Concessionaire shall prepare and provide the Authority as soon as reasonably practicable and in any event within fifteen (15) days from the date of the proposed Change of Scope, a written memorandum setting out full details of any such Change of Scope, including:
Procedure for Change of Scope. 11.2.1 In the event of the RSCL determining that a Change of Scope is necessary, it may direct the EIC/PMC to issue to the Contractor a notice specifying in reasonable detail work and services contemplated there under (the “Change of Scope Notice”).
Procedure for Change of Scope a. JMC shall whenever it desires provision of addition/deletion of works and services referred to in Article 13.1 above, issue to the Concessionaire a notice of Change of Scope (the "Change of Scope Notice") through the Independent Engineer.
Procedure for Change of Scope. 13.2.1 In the event of the Employer determining that a Change of Scope is necessary, it may direct the Employer’s Engineer to issue to the Contractor a notice specifying in reasonable detail the Works and services contemplated thereunder (the “Change of Scope Notice”).
AutoNDA by SimpleDocs
Procedure for Change of Scope. 15.6.1 MPRDC shall whenever it desires provision of additional works and services referred to in Clause 15.1 issue to the Concessionaire a notice of change of scope (the “Change of Scope Notice”).
Procedure for Change of Scope. (a) If the SPV determines that a Change of Scope is necessary, it shall issue to the Developer a notice specifying in reasonable detail the works and services contemplated thereunder (the “Change of Scope Notice”).
Procedure for Change of Scope. 57 16.3. Payments for Change of Scope 58