Common use of Delay in Responses to Submittals Clause in Contracts

Delay in Responses to Submittals. Any claim by CM/GC for a change in the Material Completion Date due to delay of responses to submittals that materially affect the completion of the Work by lengthening the critical path of the Construction Progress Schedule may be made during the time while the failure of the Design Professional to act or perform continues, or within seven days after such failure to act or perform has been cured. If no Submittal Schedule or agreement as required in Paragraph 2.1.5.2 is agreed upon, then a claim for delay will be allowed only after the Design Professional has been allowed fourteen days to take action. Any claim for extension of time or adjustment of Contract Sum must be reasonable and take into consideration the nature of the submittal.

Appears in 2 contracts

Samples: Construction Management Agreement, Construction Management Agreement

AutoNDA by SimpleDocs

Delay in Responses to Submittals. Any claim by CM/GC Contractor for a change in the Material Completion Date due to delay of responses to submittals that materially affect the completion of the Work by lengthening the critical path of the Construction Progress Schedule may be made during the time while the failure of the Design Professional to act or perform continues, or within seven days after such failure to act or perform has been cured. If no Submittal Schedule or agreement as required in Paragraph 2.1.5.2 Section 2.2.3 is agreed upon, then a claim for delay will be allowed only after the Design Professional has been allowed fourteen days to take action. Any claim for extension of time or adjustment of Contract Sum must be reasonable and take into consideration the nature of the submittal.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Delay in Responses to Submittals. Any claim by CM/GC for a change in the Material Completion Date due to delay of responses to submittals that materially affect the completion of the Work by lengthening the critical path of the Construction Progress Schedule may be made during the time while the failure of the Design Professional to act or perform continues, or within seven days after such failure to act or perform has been cured. If no Submittal Schedule or agreement as required in Paragraph Section 2.1.5.2 is agreed upon, then a claim for delay will be allowed only after the Design Professional has been allowed fourteen days to take action. Any claim for extension of time or adjustment of Contract Sum must be reasonable and take into consideration the nature of the submittal.

Appears in 1 contract

Samples: Construction Management Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.