Delay Caused By District Sample Clauses
The "Delay Caused By District" clause defines the procedures and consequences when a project delay is directly attributable to actions or inactions by the district. Typically, this clause outlines how contractors should notify the district of such delays, the documentation required to substantiate the claim, and the process for requesting extensions to the project timeline. Its core function is to ensure that contractors are not penalized for delays outside their control, thereby allocating risk fairly and maintaining project fairness.
Delay Caused By District. The dates set forth in Section 4.1.1 shall be extended on a day-for-day basis for each day of delay caused by District due to its failure to timely respond to any prior submission, as more particularly described in Section 4.2.1 below. For purposes of calculating any period of such delay, the thirty (30) day period set forth in Section