DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, and are to be distinguished from non-permissible unauthorised delays on account of which the CONTRACT PRICE of the VESSEL is subject to adjustment as provided in Article III hereof. (End of Article)
Appears in 12 contracts
Samples: Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.)
DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, and are to be distinguished from non-permissible unauthorised permissible, unauthorized delays on account of which the CONTRACT PRICE Contract Price of the VESSEL Vessel is subject to adjustment as provided for in Article III 3 hereof. (End of Article)
Appears in 4 contracts
Samples: Shipbuilding Contract (Ardmore Shipping Corp), Shipbuilding Contract (Ardmore Shipping Corp), Shipbuilding Contract (Ardmore Shipping Corp)
DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, and are to be distinguished from non-permissible unauthorised delays on account of which the CONTRACT PRICE of the VESSEL is subject to adjustment as provided in Article III hereof. (End of Article)) Hull 2749
Appears in 2 contracts
Samples: Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.)
DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, delays and are to be distinguished from non-permissible unauthorised delays on account of which the CONTRACT PRICE of the VESSEL is subject to adjustment as provided in Article III hereof. (End of Article)
Appears in 2 contracts
Samples: Shipbuilding Contract (Alma Maritime LTD), Shipbuilding Contract (Alma Maritime LTD)
DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, and are to be distinguished from non-permissible unauthorised delays on account of which the CONTRACT PRICE of the VESSEL is subject to adjustment as provided in Article III hereof. (End of Article)) Hull 2748
Appears in 2 contracts
Samples: Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.)
DEFINITION OF PERMISSIBLE DELAYS. Delays on account of the foregoing causes shall be understood to be permissible delays, delays and are to be distinguished from non-non permissible unauthorised delays unauthorized delays, on account of which the CONTRACT PRICE of the VESSEL VESSEL, is subject to adjustment as provided in Article III hereof. (End of Article).
Appears in 1 contract
Samples: Shipbuilding Contract (Tsakos Energy Navigation LTD)