Damages for delay by the Utility. In the event that (i) the Utility does not procure fulfilment or waiver of any or all of the Conditions Precedent set forth in Clause 4.1.2 within the period specified in respect thereof, and (ii) the delay has not occurred as a result of breach of this Agreement by the Supplier or due to Force Majeure, the Utility shall pay to the Supplier Damages in an amount calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for each day’s delay until the fulfilment of such Conditions Precedent, subject to a maximum of 20% (twenty per cent) of the Performance Security.
Appears in 4 contracts
Samples: Default Escrow Agreement, www.upcl.org, www.upcl.org
Damages for delay by the Utility. In the event that (i) the Utility does not procure fulfilment or waiver of any or all of the Conditions Precedent set forth in Clause 4.1.2 within the period specified in respect thereof, and (ii) the delay has not occurred as a result of breach of this Agreement by the Supplier Aggregator or due to Force Majeure, the Utility shall pay to the Supplier Aggregator Damages in an amount calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for each day’s delay until the fulfilment of such Conditions Precedent, subject to a maximum of 20% (twenty per cent) of the Performance Security.
Appears in 3 contracts
Samples: Power Supply Agreement, Pilot Power Supply Agreement, Power Supply Agreement
Damages for delay by the Utility. In the event that (i) the Utility does not procure fulfilment or waiver of any or all of the Conditions Precedent set forth in Clause 4.1.2 within the period specified in respect thereof, and (ii) the delay has not occurred as a result of breach of this Agreement by the Supplier Aggregator or due to Force Majeure, the Utility shall pay to the Supplier Aggregator Damages in an amount calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for each day’s day‟s delay until the fulfilment of such Conditions Precedent, subject to a maximum of 20% (twenty per cent) of the Performance Security.
Appears in 2 contracts
Samples: Power Supply Agreement, Power Supply Agreement
Damages for delay by the Utility. In the event that (i) the Utility does not procure fulfilment or waiver of any or all of the Conditions Precedent set forth in Clause 4.1.2 within the period specified in respect thereof, and (ii) the delay has not occurred as a result of breach of this Agreement by the Supplier or due to Force Majeure, the Utility shall pay to the Supplier Damages in an amount calculated at the rate of 0.10.5% (zero point one five per cent) of the Performance Security for each day’s delay until the fulfilment of such Conditions Precedent, subject to a maximum of 20% (twenty per cent) of the Performance Security.-and upon making such maximum, the Supplier may at its sole discretion, terminate this Agreement 8Insert the name of the coal company
Appears in 1 contract
Samples: Default Escrow Agreement
Damages for delay by the Utility. In the event that (i) the Utility does not procure fulfilment or waiver of any or all of the Conditions Precedent set forth in Clause 4.1.2 within the period specified in respect thereof, and (ii) the delay has not occurred as a result of breach of this Agreement by the Supplier or due to Force Majeure, the Utility shall pay to the Supplier Damages in an amount calculated at the rate of 0.1% (zero point one per cent) of the Performance Security for each day’s day‟s delay until the fulfilment of such Conditions Precedent, subject to a maximum of 20% (twenty per cent) of the Performance Security.
Appears in 1 contract
Samples: www.upcl.org