Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.
No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.
Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees, subcontractors, or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor shall notify the Department in writing of the delay or potential delay and describe the cause of the delay either (i) within ten (10) calendar days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result; or (ii) if a delay is not reasonably foreseeable, within five (5) calendar days after the date the Contractor first had reason to believe that a delay could result. THE FOREGOING WILL CONSTITUTE THE CONTRACTOR’S SOLE REMEDY OR EXCUSE WITH RESPECT TO ANY DELAY except if such delay is caused by the fraud, bad faith, or active interference of the Department. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy, and a rebuttable presumption of prejudice will exist based on Contractor’s untimely notice. The Contractor shall not assert any claim for damages related to such delay. The Contractor will not be entitled to an increase in the Term Contract price or payment of any kind from the Department for direct, indirect, consequential, impact, or other costs, expenses, or damages, including costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this subsection, the Department may unilaterally (and with no recourse on the part of the Contractor) identify and use an alternate source to complete any work under the Term Contract as the Department deems necessary, in its sole discretion. After the causes have ceased to exist, the Contractor shall perform at no increased cost, unless the Department determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the Department or State, in which case the Department may (i) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to the Department with respect to Products subjected to allocation; or (ii) terminate the Term Contract in whole or in part.
Compensation for Damage or Loss 1. When investments made by investors of either Contracting Party suffer loss or damage owing to war or other armed conflict which is not a result of the activities of the Contracting Party to which the investors belong, civil disturbances, revolution, riot or similar events in the territory of the latter Contracting Party, they shall be accorded by the latter Contracting Party, treatment, as regards restitution, indemnification, compensation or any other settlement, not less favourable than that that the latter Contracting Party accords to its own investors or to investors of any third State, whichever is most favourable to the investors concerned. 2. Without prejudice to paragraph 1 of this Article, investors of one Contracting Party who in any of the events referred to in that paragraph suffer damage or loss in the territory of the other Contracting Party resulting from: a) requisitioning of their property or part thereof by its forces or authorities; b) destruction of their property or part thereof by its forces or authorities which was not caused in combat action or was not required by the necessity of the situation, shall be accorded a prompt restitution, and where applicable prompt, adequate and effective compensation for damage or loss sustained during the period of requisitioning or as a result of destruction of their property. Resulting payments shall be made in freely convertible currency without delay. 3. Investor whose investments suffer damage or loss in accordance to paragraph 2. of this Article, shall have the right to prompt review of its case by a judicial or other competent authority of that Contracting Party and of valuation of its investments and payment of compensation in accordance with the principles set out in paragraph 2. of this Article.
Damage or Loss 3.1 All laptops and batteries are covered by a manufacturer’s warranty. The warranty covers manufacturer’s defects and normal use of the laptop. It does not cover negligence, abuse, malicious or accidental damage.(e.g cracked LCD screens are not covered under warranty) 3.2 Any problems, vandalism, damage loss or theft of the laptop must be reported immediately to the school. 3.3 In the case of a suspected theft a police report must be made by the family and an event number provided to the school. 3.4 In the case of accidental loss or damage a witnessed statutory declaration signed by the parent/carer should be provided and a major damage or loss report must be filled out by the student. The repair costs are subsidised. (No charge for labour). 3.5 If a laptop is damaged or lost the principal will determine whether replacement is appropriate and/or whether or not a student retains access to a laptop for home use. 3.6 Students will be required to replace lost or damaged chargers.