CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment. 12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: 12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9 12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing. 12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT (0%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion. 12.5.3.4 Subtract the aggregate of previous payments made by the Owner. 12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation. 12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions. 12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 2 contracts
Sources: Standard Form of Agreement Between Owner and Contractor (Coast Hotels & Casinos Inc), Standard Form of Agreement Between Owner and Contractor (Coast Resorts Inc)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. N/A
12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT (0percent( %). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any any, shall be as follows: N/A(If it is intended to retain additional amounts from progress payments to the Contractor beyond (1) the retainage from the Contractor's Fee provided in Clause 12.5.3.3, (2) the retainage from Subcontractors provided in Paragraph 12.7 below, and (3) the retainage, if any, provided by other provisions of the Contract, insert provision for such additional retainage here. Such provision, if made, should also describe any arrangement for limiting or reducing the amount retained after the Work reaches a certain state of completion.)
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Amisys Managed Care Systems Inc)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect [Architect] Development Manager may require. This schedule, unless objected to by the [Architect] Development Manager or the Owner, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change order.
12.5.3.2 Add If approved in advance in writing by the Owner, [Add] add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably Language indicated as being shown by strike out in the typeset document is enclosed in brackets "[" and "]" in the electronic format. stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT ten percent (010%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect and Development Manager has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General ConditionsConditions and other amounts, not including retainage described in Paragraph 12.
12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 1 contract
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of valuescompleted.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by the Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT (0%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Microware Systems Corp)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that each of the Contractor's Fee and the General Conditions shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect or the Owner may require. This schedule, unless objected to by the ArchitectArchitect or the Owner, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that the portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment Payment, as substantiated by invoices in form and substance satisfactory to the Owner, by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 .1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3,7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change Order. DPR
12.5.3.2 Add 12.5.4 If approved in advance in writing by the Owner, add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance in writing by the Owner, suitably suitable stored off the site at a location agreed upon in writing.
12.5.3.3 inwriting. Add the Contractor's Fee, less retainage of ZERO PERCENT ten percent (010%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's ’s Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 . Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 . Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 1 contract
Sources: Contract for Construction
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule Schedule of values Values submitted by the Contractor Construction Manager in accordance with the Contract Documents. The schedule Schedule of values Values shall allocate the entire Guaranteed Maximum Price (or any Separate GMP, as applicable) among the various portions Costs of the Work, except that the ContractorConstruction Manager's Fee and Fixed General Conditions shall be shown as a single separate itemline items. The schedule Schedule of values Values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect and Owner may require. If the Owner determines that the Schedule of Values is unbalanced, the Construction Manager shall, on demand, correct the Schedule before the next payment to the Construction Manager shall be made. This scheduleSchedule of Values, unless objected to by the ArchitectArchitect and the Owner, shall be used as a basis for reviewing the ContractorConstruction Manager's Applications for Payment. The Owner agrees that individual line items set forth in the Schedule of Values shall not constitute line item guarantees with respect to the Work covered by such line items. The Construction Manager shall be allowed to apply any "excess" amounts available in any line item to "shortages" in other line items provided that the GMP is not exceeded and provided that no amounts may be transferred from Cost of Work to Fixed General Conditions or used to pay items that are not reimbursable.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor Construction Manager on account of that portion of the Work for which the Contractor Construction Manager has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price (or any Separate GMP, as applicable) allocated to that portion of the Work in the schedule Schedule of valuesValues.
12.5.3 Subject to other provisions provision of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price (or any Separate GMP, as applicable) properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price (or any Separate GMP, as applicable) allocated to that portion of the Work in the schedule Schedule of valuesValues. 9Pending final determination of cost to the Owner of changes in the Work, amounts therefore shall not be included in any payment.
12.5.3.2 Add that portion of the Guaranteed Maximum Price (or any Separate GMP, as applicable) properly allocable to materials and equipment delivered and suitably suitable stored at the site Site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably suitable stored off the site Site at a location and upon terms agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT (0%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by writing with the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 1 contract
Sources: Construction Manager Agreement (Gaylord Entertainment Co /De)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage retainage. Retainage shall be 10% of ZERO PERCENT (the total billed for the first half of the project and 0%)% of the total billed for the second half of the project. The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional additional retainage, if any any, shall be as follows: N/A(If it is intended to retain additional amounts from progress payments to the Contractor beyond (1) the retainage from the Contractor's Fee provided in Clause 12.5.3.3, (2) the retainage from Subcontractors provided in Paragraph 12.7 below, and (3) the retainage, if any provided by other provisions of the Contract, insert provision for such additional retainage here. Such provision, if made, should also describe any arrangement for limiting or reducing the amount retained after the Work reaches a certain state of completion.)
Appears in 1 contract
Sources: Construction Contract (Digex Inc/De)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown known as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at the as of hte end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment equpmet delivered and suitably stored at the site for subsequent incorporation in the Work or, or if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT Ten percent (010%). The Contractor's Fee fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if iff any, indicated by the Contractor contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any any, shall be as follows: N/A(If it is intended to retain additional amounts from progress payments to the Contractor beyond (1) the retainage from the Contractor's Fee provided in Clause 12.5.3.3, (2) the retainage from subcontractors provuded in Paragraph 12.7 below, and (3) the retainage, if any, provided by other provisions of the Contract insert provision for such provision additional retainage here. Such provision, if made, should also describe any arrangement for limiting or reducing the amount retained after the Work reaches a certain state of completion.) Until the work is 50% complete, the owner will retain 10% of the amount due the contractor on accounof progress payments. At the time the work is 50% complete and thereafter, if the manner of sufficient reasons, the owner will (on presentation by the contractor of consent or surety for each application) authorize any remaining partial payments to be made in full. At substantial completion, a punch list will be established with a dollar value. The dollar value will be multiplied by 1.75 to arrive at the monies to be held until final completion is achieved.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Contractor (Essex Hospitality Associates Iv Lp)
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect Owner may require. This schedule, unless objected to by the ArchitectOwner, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price price properly allocable to the completed Work as determined by multiplying the to percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work described in Section 6.1.1, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work Work, or, if approved in advance by the Owner, suitably stored off the off-site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of ZERO PERCENT (0%). The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by as per the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentationschedule included under Article 12.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any shall be as follows: N/A
Appears in 1 contract
CONTRACTS WITH A GUARANTEED MAXIMUM PRICE. 12.5.1 Each Application for Payment shall be based upon the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Guaranteed Maximum Price among the various portions of the Work, except that the Contractor's Fee shall be shown as a single separate item. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
12.5.2 Applications for Payment shall show the percentage completion of each portion of the Work at as of the end of the period covered by the Application for Payment. The percentage completion shall be the lesser of (1) the percentage of that portion of the Work which has actually been completed or (2) the percentage obtained by dividing (a) the expense which has actually been incurred by the Contractor on account of that portion of the Work for which the Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable to the completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Guaranteed Maximum Price allocated to that portion of the Work in the schedule of values. 9Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions, even though the Guaranteed Maximum Price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage retainage. Retainage shall be 10% of ZERO PERCENT (the total billed for the first half of the project and 0%)% of the total billed for the second half of the project. The Contractor's Fee shall be computed upon the Cost of the Work described in the two preceding Clauses at the rate stated in paragraph Paragraph 5.1 or, if the Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount which bears the same ratio to that fixed-fixed sum Fee as the Cost of the Work in the two preceding Clauses bears to a reasonable estimate of the probable Cost of the Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Paragraph 12.4 to substantiate prior Applications for Payment, or resulting from errors subsequently discovered by the Owner's accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of the General Conditions.
12.5.4 Additional retainage, if any any, shall be as follows: N/A(If it is intended to retain additional amounts from progress payments to the Contractor beyond (1) the retainage from the Contractor's Fee provided in Clause 12.5.3.3, (2) the retainage from Subcontractors provided in Paragraph 12.7 below, and(3) the retainage, if any, provided by other provisions of the Contract, insert provision for such additional retainage here. Such provision, if made, should also describe any arrangement for limiting or reducing the amount retained after the Work reaches a certain state of completion.)
Appears in 1 contract
Sources: Construction Contract (Digex Inc/De)