Construction and Construction completion Clause Samples
Construction and Construction completion i. This Agreement will become unconditional and effective from the Compliance Date. Any works of whatever nature, which the Concessionaire elects to carry out prior to the Compliance Date including design or mobilisation, shall be entirely at the risk and cost of the Concessionaire. The Concessionaire shall commence the Construction Works within 30 (thirty) days from the Compliance Date.
ii. The Concessionaire shall undertake or procure the design, procurement, construction, development (modular or otherwise), completion, testing and commissioning of the Project/Project Facilities at its cost in accordance with the provisions hereof, including the approved DPR, the Specifications And Standards and Prudent Utility Practices, Applicable Laws and the terms of Applicable Permits by itself or, subject to the provisions of hereof, through Engineering Procurement Contractor(s) (EPC).
iii. The date falling at the expiry of twenty four months from the Compliance Date shall be the scheduled date for completion of Project (the "Scheduled Project Completion Date") and the Concessionaire agrees and undertakes that the Project shall be completed on or before the Scheduled Project Completion Date.
iv. The Concessionaire shall construct the Project in accordance with the Project Implementation Schedule, so annexed and approved along with the DPR. In the event that the Concessionaire fails to achieve any Project Milestone within a period of 90 (ninety) days from the date set forth for such Milestone in the Project implementation Schedule, unless such failure has occurred due to Force Majeure or for reasons solely attributable to the Concessioning Authority, it shall pay Damages to the Concessioning Authority in a sum calculated at the rate of 0.2% (zero point two per cent) of the amount of Performance Security for delay of each day until such Milestone is achieved; provided that if any or all Project Milestones or the Scheduled Project Completion Date are extended in accordance with the provisions of this Agreement, the dates set forth in the Project Implementation Schedule shall be deemed to be modified accordingly and the provisions of this Agreement shall apply as if Project Implementation Schedule has been amended as above; provided further that in the event Project Completion Date is achieved on or before the Scheduled Project Completion Date, the Damages paid under this sub clause iv., shall be refunded by the Concessioning Authority to the Concessionaire, but withou...
Construction and Construction completion. This Agreement will become unconditional and effective from the Compliance Date. Any works of whatever nature, which the Concessionaire elects to carry out prior to the Compliance Date including design or mobilisation, shall be entirely at the risk and cost of the Concessionaire. The Concessionaire shall commence the Construction Works within 30 (thirty) days from the Compliance Date. The Concessionaire shall undertake or procure the design, procurement, construction, development (modular or otherwise), completion, testing and commissioning of the Project/Project Facilities at its cost in accordance with the provisions hereof, including the approved DPR, the Specifications And Standards and Prudent Utility Practices, Applicable Laws and the terms of Applicable Permits by itself or, subject to the provisions of hereof, through Engineering Procurement Contractor(s) (EPC).