Common use of Consequences of Non-fulfillment of Conditions Precedent Clause in Contracts

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, within 180 (one hundred and eighty) days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment of any or all of the Conditions Precedent set forth in Clause 4.1.3, for any reason whatsoever, within 180 (one hundred and eighty) days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 (one hundred and eighty) days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, within 180 (one hundred and eighty) [] days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment of any or all of the Conditions Precedent set forth in Clause 4.1.3, for any reason whatsoever, within 180 (one hundred and eighty) [] days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) [] days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment fulfilment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 (one hundred and eighty) [] days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]

Appears in 1 contract

Samples: Concession Agreement

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, within 180 (one hundred and eighty) [•] days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment of any or all of the Conditions Precedent set forth in Clause 4.1.3, for any reason whatsoever, within 180 (one hundred and eighty) [•] days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) [•] days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment fulfilment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 (one hundred and eighty) [•] days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]

Appears in 1 contract

Samples: Concession Agreement

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, within 180 (one hundred and eighty) days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment fulfilment of any or all of the Conditions Precedent set forth in Clause 4.1.3, for any reason whatsoever, within 180 (one hundred and eighty) days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment fulfilment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 (one hundred and eighty) days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment fulfilment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment fulfilment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, within 180 (one hundred and eighty) days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment fulfilment of any or all of the Conditions Precedent set forth in Clause 4.1.3, for any reason whatsoever, within 180 (one hundred and eighty) days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 (one hundred and twenty) days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment fulfilment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 (one hundred and eighty) days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]

Appears in 1 contract

Samples: Concession Agreement

Consequences of Non-fulfillment of Conditions Precedent. 4.2.1 4.5.1 The Concessionaire hereby agrees and undertakes that it shall procure fulfillment of all Conditions Precedent set out in Clause 4.1.3, 4.2.1 within 180 120 (one hundred and eightytwenty) days from the date of this Agreement. In the event that (i) the Concessionaire does not procure fulfillment of any or all of the Conditions Precedent set forth in Clause 4.1.34.2.1, for any reason whatsoever, within 180 120 (one hundred and eightytwenty) days from the date of this Agreement, and (ii) the delay has not occurred as a result of breach of this Agreement by the Authority or due to Force Majeure, the Concessionaire shall be entitled to a further period not exceeding 120 90 (one hundred and twentyninety) days, subject to payment of Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the Construction Performance Security for each day of delay until the fulfillment of such Conditions Precedent; provided that the Damages specified herein shall be payable every week in advance and the period beyond the said 180 120 (one hundred and eightytwenty) days shall be granted only to the extent of Damages so paid; [provided further that no Damages shall be payable if such delay in fulfillment of Conditions Precedent has occurred solely as a result of any default or delay by the Authority in procuring fulfillment of Conditions Precedent specified in Clause 4.1.2 or due to Force Majeure.]Clause

Appears in 1 contract

Samples: Concession Agreement