Common use of Claims for Concealed or Unknown Conditions Clause in Contracts

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than seven (7) days after first observance of the conditions. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor’s cost of, or the required time for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Engineer or Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Engineer or Architect for initial determination, subject to further proceeding pursuant to these Contract Documents.

Appears in 3 contracts

Samples: Trade Contractor Agreement, Trade Contractor Agreement, Trade Contractor Agreement

AutoNDA by SimpleDocs

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or otherwise known to (or should have been known to) Contractor, or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, and should not have been known to Contractor, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than seven fourteen (714) days after first observance of the conditions. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect Owner will promptly investigate such conditions and, if they differ materially from what Contractor knew or should have known and cause an increase or decrease in the Contractor’s cost of, of or the time required time for, for performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents or that otherwise should have been known to Contractor, and that no change in the terms of the Contract is justified, the Engineer or Architect Owner shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party Contractor in opposition to such determination must be made within twenty-one thirty (2130) days after the Engineer or Architect Owner has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment determination shall be referred to arbitration as provided herein. It is expressly agreed that no adjustment in the Engineer Contract Time or Architect Contract Sum shall be permitted in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by Contractor’s (1) prior inspections, tests, reviews and preconstruction services for initial determinationthe Project, subject or (2) inspections, tests, reviews and preconstruction services which Contractor had the opportunity to further proceeding pursuant to these Contract Documentsor should have performed in connection with the Project.

Appears in 2 contracts

Samples: County Services Contract Contract, Recording Stamp Only

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party Contractor shall be given to the other party Owner promptly before conditions are disturbed and in no event later than seven ten (710) days after first observance of the conditionsconditions or after Contractor first recognizes or should have reasonably observed or discovered such condition, whichever is later. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect Owner will promptly investigate such conditions and, if the Owner determines that they differ materially and cause an increase or decrease in the Contractor’s 's cost of, or the time required time for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect Owner shall so notify the Owner Contractor and Contractor Architect in writing, stating the reasons. Claims by either party Contractor in opposition to such determination must be made within twenty-one (21) days after the Engineer or Architect Owner has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Engineer or Architect for initial determination, subject to further proceeding proceedings pursuant to these Contract Documents.Section 4.4

Appears in 1 contract

Samples: Construction Contract (NightHawk Biosciences, Inc.)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or in the Geo-technical report or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally 60 recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than seven 21 three (73) days after first observance of the conditions. Site conditions which an experienced , and prudent contractor could have anticipated by visiting in any case, prior to altering or removing the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companiesdiffering condition. The Engineer or Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor’s 's cost of, or the time required time for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or 65 Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Engineer or Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred 70 to the Engineer or Architect for initial determination, subject to further proceeding proceedings pursuant to these Paragraph 4.4. This Agreement is based closely upon the American Institute of Architects 1997 Edition of AIA Document A201, “General Conditions of the Contract Documentsfor Construction”. AIA has not granted specific authorization for this use, nor has Maricopa Community Colleges requested such use. MCCCD pays an annual license fee for unlimited use of all AIA documents. Our use is intended to be an edited version of the AIA standard documents and not intended to override or avoid copyright or other use of their documents.

Appears in 1 contract

Samples: procurement.maricopa.edu

AutoNDA by SimpleDocs

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than seven (7) days after first observance of the conditions. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor’s cost of, or the required time for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect shall so notify the Owner NURA and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Engineer or Architect has given notice of the decision. If the Owner NURA and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Engineer or Architect for initial determination, subject to further proceeding pursuant to these Contract Documents.

Appears in 1 contract

Samples: Northglenn Urban Renewal Authority