Common use of Claims for Concealed or Unknown Conditions Clause in Contracts

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 16 contracts

Samples: Agreement, Agreement, Agreement

AutoNDA by SimpleDocs

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which the Design- Builder was not aware at the time the Design-Build Contract was entered into and are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Design-Build Documents or (2) unknown physical conditions of an unusual nature, nature which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Design-Build Documents, then notice by the observing party shall be given give notice to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance of the conditions. The Architect will Owner shall promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's Design-Builder’s cost of, or time required for, performance of any part of the Work, will recommend shall negotiate with the Design-Builder an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Design-Build Documents and that no change in the terms of the Design-Build Contract is justified, the Architect Owner shall so notify the Owner and Contractor Design-Builder in writing, stating the reasons. Claims by either party the Design-Builder in opposition to such determination must be made within twenty-one (21) 21 days after the Architect Owner has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor Design-Builder cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings proceed pursuant to Paragraph 4.4Section A.4.2.

Appears in 3 contracts

Samples: www.unlv.edu, www.unlv.edu, www.unlv.edu

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect ARCHITECT/ENGINEER will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect ARCHITECT/ENGINEER determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect ARCHITECT/ENGINEER shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect ARCHITECT/ENGINEER has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect ARCHITECT/ENGINEER for initial determination, subject to further proceedings pursuant to Paragraph 4.44.

Appears in 3 contracts

Samples: Continuing Service Contract Architectural and Engineering Services, www.osceolaschools.net, www.osceolaschools.net

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days 48 hours after first observance of the conditions. The Architect Design Professional will promptly investigate such conditions and, if they the conditions differ materially and cause an increase or decrease in the Contractor's ’s cost of, or time required for, performance of any part of the Work, the Design Professional will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Design Professional determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect Design Professional shall so notify the Owner University and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 10 days after the Architect Design Professional has given notice of the decisionissued such determination. If the Owner University and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect Design Professional for initial determination, subject to further proceedings pursuant to Paragraph 4.47.09.

Appears in 3 contracts

Samples: Agreement, www.forms.procurement.wayne.edu, www.forms.procurement.wayne.edu

Claims for Concealed or Unknown Conditions. If conditions not reasonably discoverable by Construction Manager or the applicable Subcontractor are encountered at the site which are (1l) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one three (213) days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the ContractorConstruction Manager's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both, but not in the amount of Construction Manager's Fee. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents or that such differences were reasonably discoverable by Construction Manager or the applicable Subcontractor and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor Construction Manager in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one seven (217) days after the Architect has given notice of the decision. If Subject to Sections 1.1.3 and 3.2.4 hereof, if the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4the Agreement.

Appears in 2 contracts

Samples: Agreement (Chukchansi Economic Development Authority), Chukchansi Economic Development Authority

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Design- Build Documents or (2) unknown physical conditions of an unusual nature, nature which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Design-Build Documents, then the Design-Builder shall give notice by the observing party shall be given to the other party Owner promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will Owner shall promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's Design-Builder’s cost of, or time required for, performance of any part of the Work, will recommend shall negotiate with the Design-Builder an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Design-Build Documents and that no change in the terms of the Design-Build Contract is justified, the Architect Owner shall so notify the Owner and Contractor Design-Builder in writing, stating the reasons. Claims by either party the Design-Builder in opposition to such determination must be made within twenty-one (21) 21 days after the Architect Owner has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor Design-Builder cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings proceed pursuant to Paragraph 4.4Section A.4.2.

Appears in 2 contracts

Samples: cdn.cocodoc.com, homeforward.org

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 2 contracts

Samples: Immunicon Corp, Corixa Corp

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 1 contract

Samples: Agreement (Digex Inc/De)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the Project site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 7 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or and time required for, performance of for any part of the Project Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or bothSum. If the Architect determines that the conditions at the Project site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner Owner, Program Manager and Contractor in writing, stating the reasons. Claims Written objection by either party in opposition to such determination must be made within twenty-one (21) 7 days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract TimeSum, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.45.5.

Appears in 1 contract

Samples: Guaranteed Maximum Price Construction Agreement (Gaylord Entertainment Co /De)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days 24 hours after first observance of the conditions. The Architect Design Professional will promptly investigate such conditions and, if they the conditions differ materially and cause an increase or decrease in the Contractor's ’s cost of, or time required for, performance of any part of the Work, the Design Professional will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Design Professional determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect Design Professional shall so notify the Owner University and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 5 days after the Architect Design Professional has given notice of the decisionissued such determination. If the Owner University and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect Design Professional for initial determination, subject to further proceedings pursuant to Paragraph 4.48.09.

Appears in 1 contract

Samples: www.forms.procurement.wayne.edu

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and the Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Timetime, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 1 contract

Samples: Contract for Construction (Monarch Casino & Resort Inc)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect Owner will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's Design-Builder’s cost of, or time required for, performance of any part party of the Work, Work will recommend make an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect Owner shall so notify the Owner and Contractor Design-Builder in writing, stating the reasons. Claims by either party the Design-Builder in opposition to such determination must be made within twenty-one (21) 21 days after the Architect Owner has given notice of the decision. If the Owner conditions encountered are materially different, the Contract Sum and Contractor Contract Time shall be equitably adjusted, but if the parties cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4initially determined in accordance with Section A.4.2.

Appears in 1 contract

Samples: Badger State Ethanol LLC

AutoNDA by SimpleDocs

Claims for Concealed or Unknown Conditions. Claims for Concealed or Unknown Conditions: If conditions are encountered at the site which were not accessible during the pre-design and pre-construction inspections are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents taking into account that unless otherwise stipulated in Contract Documents, or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one ten (2110) days after first observance of the conditions. The Architect Owner will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's Design-Builder’s cost of, or time required for, performance of any part of the Work, will recommend consider an equitable adjustment in the Contract Sum GMP or Contract Time, or both. If the Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect Owner shall so notify the Owner and Contractor in writingDesign-Builder, stating the reasons. Claims by either party the Design-Builder in opposition to such determination must be made within twenty-one ten (2110) days after the Architect Owner has given notice of the decision. If the conditions encountered are materially different, the GMP and Contract Time shall be equitably adjusted, but if the Owner and Contractor Design-Builder cannot agree on an adjustment in the Contract Sum GMP or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4Section A.4.2.

Appears in 1 contract

Samples: bnavisionnashville.com

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 1 contract

Samples: Agreement (Digex Inc/De)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are are: (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents Documents, or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance of the conditionsdisturbed. The Architect will promptly investigate and evaluate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made and submitted within twenty-one (21) days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 1 contract

Samples: Architectural Services Agreement

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance of the conditions. The Architect Architect/Engineer will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Architect/Engineer determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect Architect/Engineer shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Architect Architect/Engineer has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect Architect/Engineer for initial determination, subject to further proceedings pursuant to Paragraph 4.410.7.

Appears in 1 contract

Samples: 00500 Agreement

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's ’s cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.

Appears in 1 contract

Samples: Form of Agreement

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, (collectively "Concealed or Unknown Conditions") then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one fourteen (2114) days after the first observance of the conditions. The Architect will promptly investigate such conditions conditions, and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, Time or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and the Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one fourteen (2114) days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.44.8.

Appears in 1 contract

Samples: Agreement (Windsor Woodmont Black Hawk Resort Corp)

Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or applicable Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and applicable Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or applicable Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph Section 4.4.

Appears in 1 contract

Samples: Agreement (Sierra Pacific Resources /Nv/)

Time is Money Join Law Insider Premium to draft better contracts faster.