Claims and Disputes. 7.1.1 A claim is a written demand or assertion by one of the parties seeking, as a matter of right, an adjustment or interpretation of this Contract, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner and Design-Builder arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 8 contracts
Samples: Hillsborough County Aviation Authority, Hillsborough County Aviation Authority, Hillsborough County Aviation Authority
Claims and Disputes. 7.1.1 11.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, an right adjustment or interpretation of this Contractthe Contract terms, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other disputes and matters in question between the Owner and Design-Builder Design Professional arising out of or relating to this Contract. All claims must be made in writing. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 8 contracts
Samples: www.tampaairport.com, Conformed Document, www.tampaairport.com
Claims and Disputes. 7.1.1 10.1.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, right an adjustment or interpretation of this Contractthe Contract Documents, payment of money, an extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner and Design-Builder arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 8 contracts
Samples: Hillsborough County Aviation Authority, Hillsborough County Aviation Authority, Hillsborough County Aviation Authority
Claims and Disputes. 7.1.1 A. A claim is a written demand or assertion by one of the parties Parties seeking, as a matter of right, an adjustment or interpretation of this Contract, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner Authority and Design-Builder Company arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 7 contracts
Samples: www.tampaairport.com, www.tampaairport.com, www.tampaairport.com
Claims and Disputes. 7.1.1 11.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, an right adjustment or interpretation of this Contractthe Contract terms, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other disputes and matters in question between the Owner and Design-Builder Consultant arising out of or relating to this Contract. All claims must be made in writing. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 7 contracts
Samples: www.tampaairport.com, General Planning Consultant and Master Plan, www.tampaairport.com
Claims and Disputes. 7.1.1 A. A claim is a written demand or assertion by one of the parties seeking, as a matter of right, an adjustment or interpretation of this Contract, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner Authority and Design-Builder Company arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 3 contracts
Samples: www.tampaairport.com, www.tampaairport.com, www.tampaairport.com
Claims and Disputes. 7.1.1 A. A claim is a written demand or assertion by one of the parties Parties seeking, as a matter of right, an adjustment or interpretation of this Contract, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question or dispute between the Owner Authority and Design-Builder Company arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 2 contracts
Samples: www.tampaairport.com, www.tampaairport.com
Claims and Disputes. 7.1.1 A. A claim is a written demand or assertion by one of the parties Parties seeking, as a matter of right, an adjustment or interpretation of this Contract, payment of money, extension of time time, or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner Authority and Design-Builder Company arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract
Claims and Disputes. 7.1.1 11.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, an right adjustment or interpretation of this Contractthe Contract terms, payment of money, extension of time or other relief with respect to the terms of this Contract. The term claim also includes other disputes and matters in question between the Owner and Design-Builder the Design Professional arising out of or relating to this Contract. All claims must be made in writing. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract
Samples: www.tampaairport.com
Claims and Disputes. 7.1.1 4.3.1 A claim Claim is a written demand or assertion by one of the parties seeking, as a matter of right, an adjustment or interpretation of this ContractContract terms, payment of money, extension of time or other relief with respect to the terms of this the Contract. The term claim “Claim” also includes other disputes and matters in question between the Owner and Design-Builder Contractor arising out of or relating to this Contractthe Contract prior to such final completion or termination. Claims must be initiated by written notice. The responsibility to substantiate claims will Claims shall rest with the party making the claimClaim.
Appears in 1 contract
Samples: Agreement (Adicet Bio, Inc.)
Claims and Disputes. 7.1.1 11.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, an right adjustment or interpretation of this Contractthe Agreement terms, payment of money, extension of time or other relief with respect to the terms of this ContractAgreement. The term claim also includes other disputes and matters in question between the Owner and Design-Builder the Consultant arising out of or relating to this ContractAgreement. All claims must be made in writing. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract
Samples: Agreement for Consulting Services
Claims and Disputes. 7.1.1 (a) A claim is a written demand or assertion by one of the parties seeking, as a matter of right, to this Agreement seeking an adjustment or interpretation of this Contractthe terms of the contract documents, payment of money, extension of time or other relief with respect to the terms of this Contractthe contract documents. The term claim “claim” also includes other disputes and matters in question between the Owner County and Design-Builder the Consultant arising out of or relating to this Contractthe contract documents. The responsibility to substantiate claims will a claim shall rest with the party making the claim.
Appears in 1 contract
Samples: agenda.myescambia.com
Claims and Disputes. 7.1.1 A claim 11.1 Claim is a written demand or assertion by one of the parties seeking, as a matter of right, seeking an adjustment or interpretation of this Contractthe terms of the Contract Documents, payment of money, extension of time or other relief with respect to the terms of this Contractthe Contract Documents. The term claim "Claim" also includes other disputes and matters in question between the Owner and Design-Design Builder arising out of or relating to this Contractthe Contract Documents. The responsibility to substantiate claims will a Claim shall rest with the party making the claimClaim.
Appears in 1 contract
Samples: Design Build Agreement
Claims and Disputes. 7.1.1 A. A claim is a written demand or assertion by one of the parties Parties seeking, as a matter of right, an adjustment or interpretation of this Supplemental Contract, payment of money, extension of time time, or other relief with respect to the terms of this Supplemental Contract. The term claim also includes other matters in question between the Owner Authority and Design-Builder Company arising out of or relating to this Supplemental Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract
Claims and Disputes. 7.1.1 1. A claim is a written demand or assertion by one of the parties Parties seeking, as a matter of right, an adjustment or interpretation of this Supplemental Contract, payment of money, extension of time or other relief with respect to the terms of this Supplemental Contract. The term claim also includes other matters in question between the Owner Authority and Design-Builder Company arising out of or relating to this Supplemental Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract
Samples: Vendor Agreement
Claims and Disputes. 7.1.1 10.1.1 A claim is a written demand or assertion by one of the parties seeking, seeking as a matter of right, right an adjustment or interpretation of this Contractthe Contract Documents, payment of money, an extension of time or other relief with respect to the terms of this Contract. The term claim also includes other matters in question between the Owner and Design-Builder Contractor arising out of or relating to this Contract. The responsibility to substantiate claims will rest with the party making the claim.
Appears in 1 contract