Capacity Test. A capacity test shall establish the Rated Capacity for a Unit and shall consist of continuous, full load operation for twenty-four hours. The result of any capacity test shall be the net electrical capacity averaged over the duration of the capacity test, expressed in MW and measured at the Point of Interconnection. Upon the conclusion of the initial capacity test, Seller may elect to either (a) within five days submit the results of such capacity test to Purchaser, witha copy to the engineer, or (b) deliver a notice to Purchaser with a copy to the engineer stating Seller's intention to perform a second capacity test no earlier than two days and no later than seven days after the Purchaser's receipt of such notice. If Seller electes to perform such second capacity test, Seller shall, within five days after the conclusion of such capacity test submit to Purchaser ("Sellers Notice") with a copy to the engineer, the results of either the initial capacity test or the second capacity test, as Seller may elect.

Appears in 1 contract

Sources: Power Purchase and Sale Contract (Aes China Generating Co LTD)

Capacity Test. A capacity test shall establish the Rated Capacity for a Unit and shall consist of continuous, full load operation for twenty-four hours. The result of any capacity test shall be the net electrical capacity averaged over the duration of the capacity test, expressed in MW and measured at the Point of Interconnection. Upon the conclusion of the initial capacity test, Seller may elect to either (a) within five days submit the results of such capacity test to Purchaser, witha with a copy to the engineer, or (b) deliver a notice to Purchaser Purchaser, with a copy to the engineer stating Seller's intention to perform a second capacity test test, commencing no earlier than two days and no later than seven days after the Purchaser's receipt of such notice. If Seller electes elects to perform such second capacity test, Seller shall, within five days after the conclusion of such capacity test submit to Purchaser ("Sellers Seller's Notice") with a copy to the engineer, the results of either the initial capacity test or the second capacity test, as Seller may elect.. During the performance of a capacity test, a unit shall operate within the limits of the Electrical System Characteristics as described in Appendix C.

Appears in 1 contract

Sources: Power Purchase and Sale Contract (Aes China Generating Co LTD)