Capacity Test. After successful completion of the Acceptance Tests, Seller shall be allowed to conduct Capacity Tests (subject to inspection by Company) in accordance with the testing procedures set forth in Attachment W (Capacity Test Procedures), to determine the Demonstrated Firm Capacity of the Facility and whether Capacity Charge payments may be EXECUTION VERSIONPuna Geothermal Venture ARTICLE 556 adjusted in accordance with Section 5.1(F) (Capacity Shortfall) and should begin in accordance with Section 5.1(G) (Commencement of Capacity Charge Payments).
Appears in 1 contract
Sources: Power Purchase Agreement (Hawaiian Electric Co Inc)
Capacity Test. After successful completion of the Acceptance Tests, Seller shall be allowed to conduct Capacity Tests (subject to inspection by Company) in accordance with the testing procedures set forth in Attachment W (Capacity Test Procedures), to determine the Demonstrated Firm Capacity of the Facility and whether Capacity Charge payments may be EXECUTION VERSIONPuna Geothermal Venture ARTICLE 556 adjusted in accordance with Section 5.1(F) (Capacity Shortfall) and should begin in accordance with Section 5.1(G) (Commencement of Capacity Charge Payments).
Appears in 1 contract
Sources: Power Purchase Agreement