Bids Exceeding Cost Estimate. If all bids exceed Consulting Architect's Final Cost Estimate, Consulting Architect, at the request of City and for no additional cost, will prepare a report for City identifying why all the bids exceed the estimate. The City has four (4) options if all bids exceed Consulting Architect's estimate. The City may: (1) give written approval of an increase in the project cost up to a maximum of 7% of the authorized total; (2) authorize rebidding of the project; (3) terminate the project and this Agreement; or (4) cooperate in revising the Project scope or specifications, or both, as necessary to reduce the construction cost. In the case of (4), Consulting Architect, without additional charge to City, shall consult with City and shall revise and modify the drawings and specifications as necessary to achieve compliance with the Consulting Architect's estimate.