Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
Appears in 15 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement, a856-cityrecord.nyc.gov
Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
Appears in 13 contracts
Samples: Construction Contract, Agreement, a856-cityrecord.nyc.gov
Application for Extension of Time. 46.8.113.8.1. Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
Appears in 10 contracts
Samples: Supply and Service Agreement, Supply and Service Agreement, a856-cityrecord.nyc.gov
Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
Appears in 1 contract
Samples: a856-cityrecord.nyc.gov