Common use of Anticipated Delay Clause in Contracts

Anticipated Delay. If Boeing concludes, based on its appraisal of the facts and normal scheduling procedures, that due to an Excusable Delay, delivery of an Aircraft will be delayed more than 12 months beyond the month in which delivery is scheduled, Boeing will promptly so notify Buyer in writing and either party may then terminate this Agreement with respect to such Aircraft by giving written notice to the other within 15 days after receipt by Buyer of Boeing's notice. Failure of a party to terminate the purchase of an Aircraft for an Excusable Delay pursuant to this paragraph results in a waiver of that party's right to terminate the purchase of such Aircraft for any delay in delivery caused by such Excusable Delay.

Appears in 6 contracts

Samples: Letter Agreement (Continental Airlines Inc /De/), Letter Agreement (Alaska Air Group Inc), Letter Agreement (Alaska Airlines Inc)