Alternative Operations Plan. (A) No later than sixty (60) calendar days after execution of the Contract, the Contractor shall submit to the County for approval a complete and detailed and satisfactory alternative operations plan for correcting, repairing or reconstructing any Facility that for any reason becomes incapable of performing its role pursuant to the Contract. This operations plan (“plans”) shall be subject to review and approval by applicable County staff, and shall include provisions for alternative Facilities if necessary and shall be of sufficient detail to satisfy the County of the Contractor's ability to maintain operations in the event that Uncontrollable Circumstances prevent the use of the primary system, or if for any other reason the Contractor is unable to Receive, Transport, and/or Dispose of Solid Waste using the primary system pursuant to this Contract. The County shall not be responsible for additional costs related to the utilization of alternative Facilities unless otherwise specified in this Contract. The Contractor shall be responsible for procuring the alternative Facilities and any and all increases in costs, including, but not limited to, transportation costs, Disposal costs, and County capital and operational costs incurred due to the need for use of the alternative Facilities. The plans shall include but not be limited to:
1.) An inventory of alternative Receiving, Transportation, and Disposal Facilities;
2.) A listing of financial and technical resources for the implementation of the plan;
3.) A mobilization plan for each component of the alternative operations system;
4.) Copies of any operating permits for alternative Facilities and/or a timeline (to be updated annually) for receiving permits that have pending applications.
(B) All alternate Facilities shall be available from the first day that operations commence under this Contract. The alternative operations plan shall be updated and submitted for County approval on an annual basis. If no changes have occurred since the last submittal that affect any part of the alternative operations system, a report stating this fact and signed by the Contractor's representative will satisfy the requirement for the annual alternative operations plan update.
(C) The County's approval of the plan is not and shall not be construed as a limitation on Contractor's obligations pursuant to the provisions of the Contract.