Common use of Adverse Weather Clause in Contracts

Adverse Weather. Shall be only weather that satisfies all of the following conditions: (1) unusually severe precipitation, sleet, snow, hail, or extreme temperature or air conditions in excess of the norm for the location and time of year it occurred based on the closest weather station data averaged over the past five years, (2) that is unanticipated and would cause unsafe work conditions and/or is unsuitable for scheduled work that should not be performed during inclement weather (i.e., exterior finishes), and (3) at the Project.

Appears in 63 contracts

Sources: General Construction Agreement, Facilities Lease, Facilities Lease

Adverse Weather. Shall be only weather that satisfies all of the following conditions: (1) unusually severe precipitation, sleet, snow, hail, or extreme temperature or air conditions in excess of the norm for the location and time of year it occurred based on the closest weather station data averaged over the past five years, (2) that is unanticipated and would cause unsafe work conditions and/or is unsuitable for scheduled work that should not be performed during inclement weather (i.e., exterior finishes), and (3) at the Project.

Appears in 6 contracts

Sources: Design Build Agreement, Design Build Agreement, Design Build Agreement

Adverse Weather. Shall be only weather that satisfies all of the following conditions: (1) unusually severe precipitation, sleet, snow, hail, heat, or extreme temperature or air cold conditions in excess of the norm for the location and time of year it occurred based on the closest weather station data averaged over the past five yearsoccurred, (2) that is unanticipated and would cause unsafe work conditions and/or is unsuitable for scheduled work that should not be performed during inclement weather (i.e., exterior finishes)unanticipated, and (3) at the Project.

Appears in 2 contracts

Sources: Facilities Lease Construction Provisions, Facilities Lease Construction Provisions

Adverse Weather. Shall be only weather that satisfies all of the following conditions: (1) unusually severe precipitationprecipitation in excess of one hald inch (0.50”) in a single day, or sleet, snow, hail, or extreme temperature or air conditions hail in excess of the norm for the location and time of year it occurred five inches (5”) in a single day, based on the closest weather station data averaged over the past five yearsdata, (2) that is unanticipated and would cause unsafe work conditions and/or is unsuitable for scheduled work that should not be performed during inclement weather (i.e., exterior finishes), and (3) at the Project.

Appears in 1 contract

Sources: General Construction Agreement