Activity Duration. The ▇▇▇▇ Contractor shall subdivide the Work into individual activities having durations of no longer than 30 Working Days each. Exceptions to this rule will be reviewed by CPRA’s Project Manager on an activity by activity basis. If multiple shifts and/or overtime are anticipated during the development of activity durations, a list of affected activities and the shift/overtime assumptions shall be provided to CPRA’s Project Manager. If requested by CPRA’s Project Manager, the ▇▇▇▇ Contractor shall furnish production rates or other information needed to justify the reasonableness of activity time durations.