Activity Duration Sample Clauses

The Activity Duration clause defines the specific time period allocated for completing a particular task or activity within a contract or project schedule. It typically sets clear start and end dates or a total number of days for the activity, ensuring all parties understand the expected timeline. By establishing these timeframes, the clause helps manage expectations, coordinate project milestones, and prevent disputes over delays or scheduling conflicts.
POPULAR SAMPLE Copied 1 times
Activity Duration. Define activities so no activity is longer than fifteen (15) days, unless specifically allowed by Architect and Owner. An exception will be granted for procurement activities.
Activity Duration. The ▇▇▇▇ Contractor shall subdivide the Work into individual activities having durations of no longer than 30 Working Days each. Exceptions to this rule will be reviewed by CPRA’s Project Manager on an activity by activity basis. If multiple shifts and/or overtime are anticipated during the development of activity durations, a list of affected activities and the shift/overtime assumptions shall be provided to CPRA’s Project Manager. If requested by CPRA’s Project Manager, the ▇▇▇▇ Contractor shall furnish production rates or other information needed to justify the reasonableness of activity time durations.
Activity Duration. Unless otherwise differently by the Authority, construction activities shall have duration from five