SCHEDULE SUBMITTALS Clause Samples
SCHEDULE SUBMITTALS. Baseline Progress Schedule Within 30 Calendar Days following the Contract Award, the ▇▇▇▇ Contractor shall prepare and submit a Baseline Progress Schedule for the entire Project to CPRA’s Project Manager for review and Approval. The Baseline Progress Schedule must be consistent with the proposed Baseline Progress Schedule submitted with the GMP. The ▇▇▇▇ Contractor will incorporate into this schedule all Project activities, activities for the placement of orders and anticipated delivery dates of materials and equipment, activities assigned to subcontractors, activities assigned to the LA DOTD or the CPRA’s Project Manager and other outside agencies (such as shop drawing reviews), and all utility Work or work by other contractors within or near the Contract limits. Schedule Updates See Section 3.3. A 30 day look ahead schedule from the approved CPM
SCHEDULE SUBMITTALS. 4.11.1. Within fifteen (15) days after execution of the Contract, the Contractor shall submit to the Architect "revision 0" of the Schedule of Values. No line item on the Schedule of Values shall exceed $25,000.00 unless acceptable to the official. In addition, in fulfillment of the Contractor's obligations to commence, prosecute and complete the Work within the Contract Time, the Con- tractor shall submit with the first Application for Payment "Revision 0" of the Contractor's Progress Schedule and the Contrac- tor's schedule of Shop Drawing submissions.
4.11.2. The Contractor shall correct, adjust or modify those schedules returned as "Revise and Resubmit", and shall resubmit Re- vision "0" schedules within the times specified. The Contractor's Revision "0" Progress Schedule shall be utilized to the fullest extent when making proposals or claims for changes in Contract Time or Contract Price.
4.11.3. The Contractor shall keep the Official informed of progress of the Work by submitting monthly Progress Schedules, which shall stay current with the Contractor's approach to Work remaining, be employed when reporting on progress or schedule recovery actions and facilitate the evaluation of payments. The Contractor shall carry on the Work and adhere to the Progress Schedule during all disputes or disagreements with the City. No Work shall be delayed or postponed pending resolution of any disputes or disagreements. The Contractor shall exercise reasonable precautions, efforts and measures to avoid or mitigate situations that would cause delays.
4.11.4. After checking and verifying that an issue of revision of the Progress Schedule complies with the applicable requirements and procedures in the Contract, the Contractor shall, within the times specified, submit to the Architect four (4) copies, or in the alternative, five (5) copies for use by the Official and the Architect plus additional copies as required by the Contractor of that Submittal bearing the Contractor's stamp of approval as representation to the City that the Contractor has determined or verified all data on that Progress Schedule, and that the Contractor and the Subcontractors and Suppliers have reviewed and coordinated the sequences in that Progress Schedule with the requirements of the Work.
4.11.5. Early Dates in the Progress Schedules shall be based on proceeding with all or part of the Work exactly on the date when the Contract Time for the Work, or designated part of the Work, commences to ru...
