Acceptance Tests. Contractor will be responsible for coordinating the Acceptance Tests of the Facility as more particularly set forth in Section 11.2 and Schedule III of this Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ (the “Testing Engineer”).
Appears in 1 contract
Sources: Engineering, Procurement and Construction Agreement (SolarBank Corp)
Acceptance Tests. Contractor will be responsible for coordinating the Acceptance Tests of the Facility as more particularly set forth in Section 11.2 and Schedule III of this Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ one or more qualified inde pendent testing companies approved by the Parties (the “Testing Engineer”).
Appears in 1 contract
Sources: Asset Purchase Agreement (SolarMax Technology, Inc.)
Acceptance Tests. Contractor will be responsible for coordinating the Acceptance Tests of the Facility as more particularly set forth in Section 11.2 and Schedule III of this Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ (the “Testing Engineer”).one
Appears in 1 contract
Sources: Engineering, Procurement and Construction Agreement
Acceptance Tests. Contractor The CONTRACTOR will be responsible for coordinating the Acceptance Tests of the Facility as more particularly set forth in Section 11.2 9.2 and Schedule III of this Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ one or more qualified independent testing companies approved by the Parties (the “Testing Engineer”).
Appears in 1 contract
Sources: Engineering, Procurement and Construction Agreement
Acceptance Tests. Contractor will be responsible for coordinating the Acceptance Tests of the Facility Facilities as more particularly set forth in Section 11.2 and Schedule III of this Agreement (the “Acceptance Tests”)Agreement. Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ Associates, D.P.C. as a qualified testing company (the “Testing Engineer”).
Appears in 1 contract
Sources: Master Engineering, Procurement and Construction Agreement (SolarBank Corp)
Acceptance Tests. Contractor will be responsible for coordinating the Acceptance Tests of the Facility as more particularly set forth in Section 11.2 and Schedule III of this Agreement (the “Acceptance Tests”). Such Acceptance Tests shall be conducted by L▇▇▇▇▇▇ one or more qualified independent testing companies approved by the Parties (the “Testing Engineer”).
Appears in 1 contract
Sources: Engineering, Procurement and Construction Agreement