Common use of ACCELERATION OF THE WORK Clause in Contracts

ACCELERATION OF THE WORK. § 3.4.1 If during the course of construction the Owner or Architect determines that the performance of the Work has not progressed or reached the level of completion required by the current, approved Construction Schedule, the Owner shall have the right to order the Contractor to take corrective measures as necessary to restore the progress of the construction to the requirements of such schedule, including but not limited to (1) working additional shifts or overtime, (2) finishing additional labor, services, materials, equipment and facilities and (3) other similar acceleration measures. The costs incurred by the Contractor pursuant to this Section 3.4.1 shall be paid by the Contractor.

Appears in 5 contracts

Samples: resources.finalsite.net, resources.finalsite.net, resources.finalsite.net

AutoNDA by SimpleDocs

ACCELERATION OF THE WORK. § 3.4.1 2.4.1 If during the course of construction the Owner or Architect determines that the performance of the Work has not progressed or reached the level of completion required by the current, approved Construction Schedule, the Owner shall have the right to order the Contractor to take corrective measures as necessary to restore the progress of the construction to the requirements of such schedule, including but not limited to (1) working additional shifts or overtime, (2) finishing furnishing additional labor, services, materials, equipment and facilities and (3) other similar acceleration measures. The costs incurred by the Contractor pursuant to this Section 3.4.1 2.4.1 shall be paid by the Contractor.

Appears in 1 contract

Samples: homeforward.org

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.