Workscope. The following works must be undertaken by UE. List to be provided but may include – Upgrade or installation of a distribution substation or other works. Undertake assessment of the generator connection and prepare a report. Review opportunities for the generator to provide network support and to receive avoided Distribution Use of System (DUoS) and Transmission Use of System (TUoS) payments. Provide advice to the Generator’s contractor on protection and control design to satisfy UE access standards. Install an operator warning label within the distribution substation and update the UE generator register and GIS. Witness generator commissioning tests if required. Review commissioning test report. Prepare the generator connection agreement.
Appears in 2 contracts
Sources: Distribution Connection Embedded Generator Agreement, Distribution Connection Embedded Generator Agreement