Whenever a Relief. Event occurs and DBT submits an original or supplemental Notice of Potential Relief Event for Extra Work Costs, DBT shall concurrently submit to KYTC an analysis of potential re-sequencing, re-scheduling, and other work-around measures and a comparison of the estimated costs thereof to the estimated savings in the Extra Work Costs that would result.
Appears in 2 contracts
Sources: Design Build Agreement, Design Build Agreement