Common use of Weekly Progress Reports Clause in Contracts

Weekly Progress Reports. Subcontractor shall be required to submit weekly progress reports which shall contain a status report concerning any and all of Subcontractor’s Work under this Subcontract which is currently in progress, regardless of the location of such Work. Said reports shall show the progress of manufacture, preparation, and installation in such detail as may be required by Contractor, including plans, drawings, or diagrams. Subcontractor shall also include with the progress report a “construction look ahead” which specifies the work Subcontractor expects to perform in the next three (3) succeeding weeks.

Appears in 2 contracts

Sources: Subcontract Agreement, Subcontract Agreement