Weather. Any rainfall, temperatures below 32 degrees Fahrenheit or winds greater than 25 m.p.h. which actually prevents Work on a given day, shall be considered lost time and an additional day added to the Contract Time, provided no work could be done on site, and provided written notice has been submitted to the Owner by the Contractor documenting same.
Appears in 3 contracts
Samples: Construction Agreement, Construction Agreement, Construction Agreement
Weather. Any During the Construction Phase, any rainfall, temperatures below 32 degrees Fahrenheit or winds greater than 25 m.p.h. which actually prevents Work on a given day, shall be considered lost time and an additional day added to the Contract Time, provided no work could be done on site, and provided written notice has been submitted to the Owner by the Contractor Construction Manager documenting same.
Appears in 3 contracts
Weather. Any rainfallDuring the Construction Phase, any rainfall temperatures below 32 degrees Fahrenheit or winds greater than 25 m.p.h. which actually prevents Work on a given day, shall be considered lost time and an additional day added to the Contract Time, provided no work could be done on site, and provided written notice has been contemporaneously submitted to the Owner by the Contractor Construction Manager documenting same.
Appears in 1 contract
Samples: Agreement
Weather. Any During the Construction Phase, any rainfall, temperatures below 32 degrees Fahrenheit or winds greater than 25 m.p.h. which actually prevents Work on a given day, shall be considered lost time and an additional day added to the Contract Time, provided no work could be done on site, and provided written notice has been submitted to the Owner by the Contractor Construction Manager documenting same.. SAMPLE
Appears in 1 contract
Samples: Agreement