Volt/Var Optimization Clause Samples

Volt/Var Optimization a. The BESS will produce or absorb reactive power (“VARs”) such that the grid voltage is regulated towards a nominal value. b. The exact volt/var response curve will be agreed upon by GPA and Owner, and will take into account the ▇▇▇▇ operating parameters/limits. 1. NTP for preliminary engineering studies and 60% design. 10/31/2023 2. EPC Vendor Selection 1/15/2024 or 60 days after PUC approval 3. Long Lead Items Vendors Selection 1/30/2024 4. Contract Consultant to Conduct Interconnection System Impact Study 3/15/2024 5. Long Lead Items Vendors Contracting 3/31/2024 6. EPC Contract Signing and Notice to Proceed 6/30/2024