To be Processed as a Part of the Change Order Process. Extensions of Time and compensation for Time Dependent Overhead Costs for Force Majeure are to be processed as a Change Order pursuant to Article 3.2.6.
To be Processed as a Part of the Change Order Process. Extensions of Time and compensation for Time Dependent Overhead Costs for Unavoidable Delay are to be processed as a Change Order pursuant to Article 3.2.6.
To be Processed as a Part of the Change Order Process. Extensions of Time and adjustments to the Contract Sum for compensable Unavoidable Delay are to be processed as a Change Order pursuant to Section 3, Part 4.
To be Processed as a Part of the Change Order Process. Extensions of Time and adjustments to the Contract Sum for Force Majeure are to be processed as a Change Order pursuant to Section 3 Part 4. No adjustment to the Contract Sum will be allowed.
To be Processed as a Part of the Change Order Process. Extensions of Time and adjustments to the Contract Sum for Force Majeure are to be processed as a Change Order pursuant to Paragraph 3.4.6.