Time for Substantial Completion Sample Clauses

Time for Substantial Completion. Landlord shall cause the Tenant Improvements to be Substantially Completed according to the Approved Final Plans, and in compliance with all Laws in effect as of the time of filing for the building permit and this Lease, on or before the Target Occupancy Date (as may be extended as provided in Section 2.01(n)). No Tenant Improvements which have not been completed and which would affect materially Tenant’s use or operations shall be included in the Punch-List. Landlord shall provide Tenant with not less than thirty (30) days advance written notice of the estimated Date of Substantial Completion if such date varies from the Target Occupancy Date. In the event Landlord fails to provide such notice, and if such notice is required, the Date of Substantial Completion shall not be earlier than thirty (30) days after the date of such notice from Landlord.
AutoNDA by SimpleDocs
Time for Substantial Completion. Subject to delays resulting from Tenant Delays (as that term is defined in the Workletter Agreement), Landlord shall use commercially reasonable efforts to cause the Leased Premises to be Substantially Completed according to the Plans (as that term is defined in the Workletter Agreement) on or before the Scheduled Commencement Date. Notwithstanding anything to the contrary set forth herein (including the fact that the Term has not commenced), the obligation of the Tenant to pay Minimum Rent and Additional Rent hereunder shall commence on the date, as reasonably determined by Landlord, on which the Leased Premises would have been Substantially Completed but for Tenant Delays. Landlord shall provide Tenant with not less than five (5) days' advance written notice of the estimated date of Substantial Completion if such date varies by more than five (5) days from the Scheduled Commencement Date. In the event Landlord fails to provide such notice, and if such notice is required, the date of Substantial Completion shall not be earlier than ten (10) days from the date of such notice from Landlord.
Time for Substantial Completion. The Building shall be substantially completed not later than March 31st, 2006. Unavoidable delays solely caused by, or arising out of, adverse weather conditions, unforeseeable labor or material shortages, action of the civil authorities or any other cause beyond the control of Landlord shall extend the construction completion date on a day for day basis, provided that Landlord notifies Tenant of such occurrence within five (5) calendar days after the start of any such delay and within five (5) calendar days after the resumption of work.
Time for Substantial Completion. LESSOR shall cause Contractor to ------------------------------- diligently pursue the construction and cause the Substantial Completion of the Tenant Improvements on or before a date which is no later than forty-five (45) days following the date of LESSEE's delivery of the Building Permit to LESSOR ("Scheduled Completion Date"); provided, however, the Scheduled Completion Date shall be extended if Substantial Completion is delayed on account of (a) changes to the approved Tenant Improvement Plans requested by LESSEE, including time expended in obtaining fixed, price quotations for any changed work as required under subsection 6.1.7 of this Addendum or delays in obtaining LESSEE's approval of any Government Changes as provided in subsection 6.1.1 of this Addendum, (b) Government Changes, (c) delays of LESSEE in paying the amount of any Tenant Improvement Costs payable by LESSEE, or (d) fire, earthquake or other causalities, inclement weather conditions, delays encountered in processing governmental approvals or inspections or other governmental action which prevents or impedes the orderly progress of construction, delays encountered as a result of the discovery of any unknown or concealed conditions affecting the Premises, delays caused by general area wide labor or material shortages or labor disputes (such as strikes or lock-outs), or any other causes beyond the reasonable control of LESSOR or Contractor. If such delays are encountered, the Scheduled Completion Date shall be extended but only for the number of days the delaying event exists and prevents Contractor from proceeding with the work. The extension of the Scheduled Completion Date pursuant to this subsection shall not change or delay the date for LESSEE to commence payment of the Base Rent, Operating Expenses or other charges payable by LESSEE. Except for excused delays described in the preceding provisions, if Substantial Completion is delayed beyond the Scheduled Completion Date, the following provisions shall apply: (i) if the delay does not exceed thirty (30) days, LESSEE shall be credited with two (2) free days of Base Rent for each one (1) day Substantial Completion is so delayed, with such credits to be applied to the Base Rent next becoming due; and (ii) if the delay exceeds thirty (30) days, then LESSEE at its option, shall have the right to either (aa) continue to accumulate the two (2) days free Base Rent credit for each one (1) day of additional delay and apply such credit to Base R...
Time for Substantial Completion. The Agreement’s original Contract Time for Substantial Completion of all construction work was 126 calendar days from the date of commencement. The Contract Time for Substantial Completion is increased to 156 calendars from the date of commencement to allow Contractor to perform the Work described in the Agreement as well as the repair work described herein. Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to the Agreement.
Time for Substantial Completion 

Related to Time for Substantial Completion

  • Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.

  • Substantial Completion “Substantial Completion” means the stage in the progress of the Work when the Work, or designated portions thereof, may still require minor modifications or adjustments but, in the Owner’s opinion, the Work has progressed to the point such that all parts of the Work under consideration are fully operational and usable for intended purposes, as evidenced by a Certificate of Substantial Completion approved by the Owner. If a Certificate of Occupancy is required by public authorities having jurisdiction over the Work, said certificate shall be issued before the Work or any portion thereof is considered substantially complete. When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall notify Owner’s Designated Representative (sometimes referred to as the “ODR”) and request a determination as to whether the Work or designated portion thereof is substantially complete. If the ODR does not consider the Work substantially complete, the ODR will notify the Contractor giving reasons therefore. Failure on the Owner’s part to list a reason does not alter the responsibility of the Contractor to complete all Work in accordance with the terms of this Agreement. After satisfactorily completing items identified by Owner’s Designated Representative, the Contractor shall then submit another request for the ODR to determine Substantial Completion. If The ODR considers the Work substantially complete, The ODR will prepare and deliver a certificate of Substantial Completion which shall establish the date of Substantial Completion, shall include a punch list of items to be completed or corrected before final completion and final payment, shall establish the time within which the Contractor shall finish the punch list, and shall establish responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work, warranty and insurance. Failure to include an item on the punch list does not alter the responsibility of the Contractor to complete all Work in accordance with the terms and conditions of this Agreement. The certificate of Substantial Completion shall be signed by the Owner and the Contractor to evidence acceptance of the responsibilities assigned to them in such certificate. Substantial Completion (as defined in this agreement) for all stages of the Work shall be achieved on or before the following Substantial Completion date: DATE FOR SUBSTANTIAL COMPLETION: TBD Under no circumstances will the time for Substantial Completion exceed this date without a written amendment to this Agreement. THE TIMES SET FORTH IN THE CONSTRUCTION DOCUMENTS ARE AN ESSENTIAL ELEMENT OF THE AGREEMENT. TIME LIMITS STATED IN THE CONTRACT DOCUMENTS ARE OF THE ESSENCE OF THIS AGREEMENT.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be: (Check one of the following boxes.) [ « » ] The date of this Agreement. [ « » ] A date set forth in a notice to proceed issued by the Owner. [ « » ] Established as follows: (Insert a date or a means to determine the date of commencement of the Work.) « » If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

  • Completion of Repairs Borrower will commence any Repairs as soon as practicable after the date of this Loan Agreement and will diligently proceed with and complete such Repairs on or before the Completion Date. All Repairs and Capital Replacements will be completed in a good and workmanlike manner, with suitable materials, and in accordance with good building practices and all applicable laws, ordinances, rules, regulations, building setback lines and restrictions applicable to the Mortgaged Property. Borrower agrees to cause the replacement of any material or work that is defective, unworkmanlike or that does not comply with the requirements of this Loan Agreement, as determined by Lender.

  • COMMENCEMENT AND COMPLETION OF THE PROJECT Section 3.01 The Project

  • Certificate of Substantial Completion The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the City when construction is sufficiently complete, in accordance with the Contract Documents, so the City of Roanoke, Virginia (City or Owner) can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents. ITB NO.: PROJECT: CONTRACTOR: PROJECT OR DESIGNATED PORTION SHALL INCLUDE: . The Work or portion thereof designated above performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as . The City will assume possession thereof at a.m./p.m. on that date. A list of items ("punch list"), prepared by the A/E and/or Director, Department of Public Works, to be completed or corrected by the Contractor, is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The Contractor will complete any portion of the Work that is not substantially complete and will complete or correct the work on the punch list in accordance with the Contract Documents. The establishment of a date of substantial completion and/or the acceptance of the Work or designated portion thereof does not relieve the Contractor of any responsibility for any faulty materials or workmanship or operate to relieve the Contractor or its Surety from any obligation under the Contract with the City or the Performance Bond or Labor and Material Payment Bond. This Certificate is subject to the terms and conditions of the Contract Documents, including but not limited to Section 20.8 of the General Conditions. Contractor By Date City of Roanoke, Virginia City By Date CITY OF ROANOKE, VIRGINIA AFFIDAVIT OF PAYMENT OF CLAIMS By: (Insert Exact Name and Address of Firm) This day personally appeared before me, , a Notary Public in and for the City (County) of , and, being by me first duly sworn states that all subcontractors and suppliers of labor and materials have been paid all sums due them for work performed or materials furnished in the performance of the Contract between the City of Roanoke, Virginia, and ,Contractor, dated , 20 , for or arrangements have been made by the Contractor satisfactory to such subcontractors and suppliers with respect to the payment of such sums as may be due from the Contractor to the subcontractors and suppliers. CONTRACTOR: BY: PRINTED OR TYPED NAME AND TITLE: COMMONWEALTH OF VIRGINIA CITY/COUNTY OF I, , a Notary Public in and for the Commonwealth of Virginia, do hereby certify that , whose name is signed to the foregoing, has subscribed, sworn to and acknowledged the same before me this day of , 20 . Seal: Notary Public Registration #: My Commission Expires: CITY OF ROANOKE, VIRGINIA

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Completion of the Work The Contractor must obtain Material Completion as defined in Section 6.1.2 below prior to any occupancy of the Project.

  • Completion of the Project The Contracting Party shall complete the construction, equipping and furnishing of the Improvements in accordance with the Plans and submit to the Board a Certificate of Completion on or before November 1, 2016.