Test schedule Sample Clauses

Test schedule. 6.4.1. To evaluate the vehicle stability control function the tests used shall be agreed between the system/vehicle manufacturer and the Technical Service and shall include conditions, appropriate to the function being evaluated, that would without the intervention of the stability control function result in loss of directional control or roll-over. The dynamic manoeuvres, test conditions and results shall be included in the test report.
AutoNDA by SimpleDocs
Test schedule. Seller shall submit its start-up and test schedule for the Project for PPUC's review at least sixty (60) Days prior to start up and testing to establish the Commercial Operation Date as contemplated by Section 4.3 and Schedule 2.
Test schedule. The testing covered by this agreement begins when each of the three tests—Caterpillar C13, Cummins ISB, and Xxxx T-12—have been formally affirmed "ready for matrix testing" by the ASTM HDEOCP and all other conditions shown above under Scope have been met. The targeted completion date for each engine test for the ASTM PC-10 test matrix is ? months after its commencement date. The commencement date is the date that the first test begins. Extension of the timing past this targeted completion date must be approved by the PC-10 NCDT and DEOAP.
Test schedule. Within ___ days of the date of this Agreement; Consultant shall deliver to Client a test schedule designed to identify when such unit and integrated testing of the Technology shall occur in order to meet the time frames identified by the parties. ____________ guarantees that it shall make available to Client testing resources (including equipment and staff) necessary to perform the testing identified in the Schedule at the identified times.
Test schedule. Phase 1 – Establish starting conditions: Bring Project to 0% State of Charge.
Test schedule. The test procedure comprises a number of consecutive braking cycles each containing a number of X braking intervals of 5 seconds brake applied followed by 10 seconds brake released. No of cycle Number of brake application s X Initial brake rotor temperature (EC) Forced cooling 1 5 100 yes 2 5 increasing # 200 no 3 5 200 no 4 5 increasing # 300 no 5 5 300 no 6 3 250 yes 7 3 200 yes 8 3 150 yes 9 10 100 yes 10 5 increasing # 300 no 11 5 300 no

Related to Test schedule

  • First Schedule Liquidated Damages

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Delivery Schedule The scheduled months of delivery of the Aircraft are listed in the attached Table 1. Exhibit B describes certain responsibilities for both Customer and Boeing in order to accomplish the delivery of the Aircraft.

  • COMPLETION SCHEDULE 6.1 The proposed schedule for the completion of the Project is presented in “Attachment D” and is made a part hereof.

  • Budget Schedule Subrecipient agrees that the expenditures of any and all funds under this Contract will be in accordance with the Budget Schedule, a copy of which is attached hereto as Attachment C, and which by this reference is incorporated herein and made a part hereof as if fully set forth.

  • Outage Schedules The Connecting Transmission Owner shall post scheduled outages of its transmission facilities on the NYISO OASIS. Developer shall submit its planned maintenance schedules for the Large Generating Facility to Connecting Transmission Owner and NYISO for a minimum of a rolling thirty-six month period. Developer shall update its planned maintenance schedules as necessary. NYISO may direct, or the Connecting Transmission Owner may request, Developer to reschedule its maintenance as necessary to maintain the reliability of the New York State Transmission System. Compensation to Developer for any additional direct costs that the Developer incurs as a result of rescheduling maintenance, including any additional overtime, breaking of maintenance contracts or other costs above and beyond the cost the Developer would have incurred absent the request to reschedule maintenance, shall be in accordance with the NYISO OATT. Developer will not be eligible to receive compensation, if during the twelve (12) months prior to the date of the scheduled maintenance, the Developer had modified its schedule of maintenance activities other than at the direction of the NYISO or request of the Connecting Transmission Owner.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

Time is Money Join Law Insider Premium to draft better contracts faster.