Test Elements. The Efficiency Rate Tests shall be conducted as follows (unless Buyer otherwise agrees in writing in its sole discretion): 1. At the start of the Efficiency Rate Test, the Stored Energy of the Energy Storage System shall be reduced to an amount equal or less than [20%] State of Energy, which Stored Energy amount (“Stored Energytest,0”) shall be recorded. 2. The Project shall be charged with Charging Energy to bring the Stored Energy of the Energy Storage System to at least [80%] State of Energy, at the then-applicable Contract Capacity, which Charging Energy amount (“Charging Energytest”) and Stored Energy amount at the end of such charging (“Stored Energytest,1”) shall be recorded. 3. Following the expiration of up to 24 hours after the end of such charging, the Scheduling Coordinator for the Project shall schedule the Project for discharging, at the Contract Capacity in an amount equal to the product of Charging Energytest multiplied by the Guaranteed Round-Trip Efficiency Rate. The Delivered Amount at the end of such discharging (“Delivered Energytest”) and the Stored Energy amount at the end of such discharging (“Stored Energytest,2”) shall be recorded.
Appears in 2 contracts
Sources: Energy Storage Power Purchase Agreement, Energy Storage Power Purchase Agreement
Test Elements. The Efficiency Rate Tests shall be conducted as follows (unless Buyer ▇▇▇▇▇ otherwise agrees in writing in its sole discretion):
1. At the start of the Efficiency Rate Test, the Stored Energy of the Energy Storage System shall be reduced to an amount equal or less than [20%] State of Energy, which Stored Energy amount (“Stored Energytest,0”) shall be recorded.
2. The Project shall be charged with Charging Energy to bring the Stored Energy of the Energy Storage System to at least [80%] State of Energy, at the then-applicable Contract Capacity, which Charging Energy amount (“Charging Energytest”) and Stored Energy amount at the end of such charging (“Stored Energytest,1”) shall be recorded.
3. Following the expiration of up to 24 hours after the end of such charging, the Scheduling Coordinator for the Project shall schedule the Project for discharging, at the Contract Capacity in an amount equal to the product of Charging Energytest multiplied by the Guaranteed Round-Trip Efficiency Rate. The Delivered Amount at the end of such discharging (“Delivered Energytest”) and the Stored Energy amount at the end of such discharging (“Stored Energytest,2”) shall be recorded.
4. The Tested Round-Trip Efficiency Rate (TRTER) shall be calculated as follows: TRTER =