Synchronization,CommissioningandCommercialOperation Sample Clauses
Synchronization,CommissioningandCommercialOperation. 5.1.1 The SPG shall give at least thirty (30) days’ advanced preliminary writtennotice and at least fifteen (15) days’ advanced final written notice, of the date onwhichitintendsto synchronizetheSolarPowerProjecttothe Grid System.
5.1.2 Subject to Article 5.1.1, the Power Project may be synchronized by the SPG to theGrid System when it meets all the connection conditions prescribed in applicableGrid Code then in effect and otherwise meets all other Indian legal requirements for synchronization to the Grid System.
5.1.3 Thesynchronizationequipmentandallnecessaryarrangements/equipmentincl ▇▇▇▇▇ RTU for scheduling of power generated from the Project and transmissionof data to the concerned authority as per applicable regulation shall be installed bythe SPG at its generation facility of the Power Project at its own cost. The SPG shallsynchronizeitssystemwiththeGridSystemonlyaftertheapprovalofsynchro nization scheme is granted by the head of the concerned substation/ andchecking/verificationismadebytheconcernedauthoritiesofthe.
5.1.4 The SPG shall immediately after each synchronization/tripping of generator, informthesub- stationoftheGridSystemtowhichthePowerProjectiselectricallyconnected in accordance with applicable Grid Code. In addition, the SPG will injectin-firm power to grid from time to time to carry out operational/ functional test prior tocommercial operation. For avoidance of doubt, it is clarified that Synchronization /ConnectivityoftheProjectwiththegridshallnottobeconsideredasCommissioni ngoftheProject.
5.1.5 The SPG shall commission the Project within nine (9) Months from the Date ofexecution of this PPA. Declaration of COD shall be certified by the commissioningcommittee.
5.1.6 ThePartiesagreethatforthepurposeofcommencementofthesupplyofelectricity bySPGto,liquidateddamagesfordelayetc.,theScheduledCommissioningDate asdefined inthisAgreementshallbethe relevant date.