Switching schedule Sample Clauses

A Switching Schedule clause defines the specific times or conditions under which a transition or changeover between systems, services, or operational modes will occur. In practice, this clause might outline the exact dates and procedures for switching from one supplier to another, or for moving from an old system to a new one, ensuring all parties are aware of their responsibilities during the transition. Its core function is to provide a clear, agreed-upon timeline and process for changeovers, minimizing confusion and reducing the risk of service interruptions or disputes.
POPULAR SAMPLE Copied 3 times
Switching schedule. In the event of faults needing switchings which will affect the cross-border link, Statnett and Svenska Kraftnät are to be informed before any switchings are made. In the case of switchings on the Swedish grid, switching schedules are to be drawn up by Svenska Kraftnät.
Switching schedule. Switchings on the links are carried out in accordance with a switching schedule drawn up by Svenska Kraftnät. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations.
Switching schedule. Switchings on the links are carried out in accordance with a switching schedule drawn up by the Party with the outage requirement. The Party drawing up the switching schedule is also the switching responsible operator.
Switching schedule. Prior to planned outages on the HVDC links, written confirmation shall be exchanged between Statnett’s Regional Centre in Oslo and ▇▇▇▇▇▇▇▇▇.▇▇’s control room at Tjele. Outage planning for the links will be carried out in accordance with 4.5.
Switching schedule. Switching concerning Konti-Skan takes place as follows:  Switching which concerns ▇▇▇▇▇▇ ▇▇▇▇▇▇▇ alone takes place in accordance with a switching schedule drawn up by ▇▇▇▇▇▇▇▇▇.▇▇.  Switching on the Danish part of the cable takes place in accordance with a switching plan drawn up by ▇▇▇▇▇▇▇▇▇.▇▇. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations.  Switching in Lindome alone takes place in accordance with a switching plan drawn up by SvK.  Switching on the Swedish part of the cable takes place in accordance with a switching schedule drawn up by SvK. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations.
Switching schedule. Switchings on the 400 kV links are carried out in accordance with a switching schedule drawn up by Svenska Kraftnät. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations. Switching concerning ▇▇▇▇▇-▇▇▇▇ 1 and 2 takes place as follows: • The necessary switching required to switch off, earth and issue switching confirmations for the polar cables is implemented in accordance with switching schedules drawn up by Svenska Kraftnät. Templates for these switching schedules have been drawn up jointly between Fingrid and Svenska Kraftnät. • Switching in Rauma alone takes place in accordance with a switching plan drawn up by ▇▇▇▇▇▇▇. • Switching in Dannebo or Finnböle alone takes place in accordance with a switching schedule drawn up by Svenska Kraftnät.
Switching schedule. Switchings on the links are carried out in accordance with a switching schedule drawn up by Svenska Kraftnät. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations. Switching concerning ▇▇▇▇▇-▇▇▇▇ takes place as follows:  Switching in Rauma alone takes place in accordance with a switching plan drawn up by Fingrid.  Switching on the Finnish part of the cable takes place in accordance with a switching plan drawn up by Fingrid. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations.  Switching in Dannebo alone takes place in accordance with a switching schedule drawn up by SvK.  Switching on the Swedish part of the cable takes place in accordance with a switching schedule drawn up by SvK. Before the work begins, the Operations Centres shall confirm that the link is grounded and secured against switching on by exchanging switching confirmations.

Related to Switching schedule

  • Working Schedule The hours and days of work of each employee shall be posted in an appropriate place at least two (2) weeks in advance. The Employer shall, after agreement with the Union, set forth the working schedule of each department, hereinafter referred to as the "Work Schedule". The schedule shall only be altered to meet emergency situations. No employee shall be scheduled to work a split shift unless mutually agreed to.

  • Operating Schedule Purchaser shall, be- fore commencing operations, provide in writing an annual Operating Schedule of anticipated major activities and needs for logging Included Timber, such as logging, road maintenance, Scaling, and road construction, including construction staking under B5.212 and material delivery under B5.22. Upon reasonable notice to Forest Service, such schedule shall be subject to modifications necessi- ▇▇▇▇▇ by weather, markets, or other unpredictable circum- stances.

  • Vesting Schedule Except as provided in Section 4, and subject to Section 5, the Restricted Stock Units awarded by this Award Agreement will vest in accordance with the vesting provisions set forth in the Notice of Grant. Restricted Stock Units scheduled to vest on a certain date or upon the occurrence of a certain condition will not vest in Participant in accordance with any of the provisions of this Award Agreement, unless Participant will have been continuously a Service Provider from the Date of Grant until the date such vesting occurs.

  • Local Circuit Switching Capability, including Tandem Switching Capability 4.2.1 Local circuit switching capability is defined as all line-side and trunk-side facilities, plus the features, functions, and capabilities of the switch. The features, functions, and capabilities of the switch shall include the basic switching function of connecting lines to lines, lines to trunks, trunks to lines, and trunks to trunks. Local circuit switching includes all vertical features that the switch is capable of providing, including custom calling, custom local area signalling service features, and Centrex, as well as any technically feasible customized routing functions. 4.2.2 Notwithstanding BellSouth’s general duty to unbundle local circuit switching, BellSouth shall not be required to unbundle local circuit switching for ▇▇▇▇ when ▇▇▇▇: (1) serves an End User with four (4) or more voice-grade (DS0) equivalents or lines served by BellSouth in Zone 1 of one of the following MSAs: Atlanta, GA;

  • Pricing Schedule 7.1. The Pricing Schedule sets out details of the pricing of the Services. 7.2. The prices in the Pricing Schedule are not to be increased for the period of the Contract. 7.3. Accordingly, the Service Provider may not unilaterally increase the prices in the Pricing Schedule. But nothing in the Contract prevents the Service Provider from improving on the prices in the Pricing Schedule for the purposes of a particular Order.