Suspensions of Work Ordered by the Engineer Clause Samples

The "Suspensions of Work Ordered by the Engineer" clause grants the engineer the authority to temporarily halt construction or related activities on a project. In practice, this means the engineer can issue formal instructions to pause work for reasons such as safety concerns, unforeseen site conditions, or the need for design changes. The clause typically outlines the procedures for notifying the contractor, the duration of the suspension, and any adjustments to the project timeline or costs. Its core function is to provide a structured process for managing interruptions, ensuring that both parties understand their rights and obligations during periods when work must be stopped.
POPULAR SAMPLE Copied 1 times
Suspensions of Work Ordered by the Engineer. 1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment. 2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted. 3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed. 4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
Suspensions of Work Ordered by the Engineer. 1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the 2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted. 3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed. 4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
Suspensions of Work Ordered by the Engineer. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.
Suspensions of Work Ordered by the Engineer. This clause provides for the adjustment of the contract terms if the performance of all or a portion of the work is suspended or delayed by the Engineer, in writing, for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry). The contractor is required to submit a request for adjustment, in writing, to the Engineer within 7 calendar days of receipt of the notice to resume work. Recovery of profit on costs resulting from suspensions of work is not allowed. 1. This clause does not preclude the recognition of constructive suspensions or delays resulting from the contracting agency's actions, without written notification. These are delays caused by the owner's instructions that are not in writing. The contractor may receive verbal orders from the engineer, or be delayed by the owners' lengthy review of submittals. Some states recognized constructive delays in their specifications prior to the FHWA regulation. The preamble to the regulation indicates that states may continue to recognize construction delays if this is provided in their standard specifications and contract administration procedures. 2. To qualify for an adjustment, suspensions must be for unreasonable periods and do not include brief, customary suspensions for reasons inherent to highway construction (i.e., material sampling and testing; approval of shop drawings, material sources, etc.; and other reasonable and customary suspensions necessary for the supervision of construction by the contracting agency). In addition, an adjustment under this clause is not allowed if the work is suspended for other reasons or if an adjustment is provided for, or excluded, under other terms or conditions of the contract.