Study Process. Repower Requests will consist of an environmental study as set forth in Section 14.5.1 and may consist of two additional studies: (1) A system impact study for the Repower Request (Repower Impact Study) as set forth in Section 14.5.2, and (2) a Facilities Study for the Repower Request (Repower Facilities Study) as set forth in Section 14.5.3.
Appears in 2 contracts
Sources: Standard Large Generator Interconnection Procedures (Lgip), Settlement Agreement
Study Process. Repower Requests will consist of an environmental study as set forth in Section 14.5.1 and may consist of two additional studies: (1) A system impact study for the Repower Request (Repower Impact Study) as set forth in Section 14.5.2, and (2) a Facilities Study for the Repower Request (Repower Facilities Study) as set forth in Section 14.5.3.and