Site Responsibility Schedule Sample Clauses

A Site Responsibility Schedule is a clause that outlines the specific duties and obligations assigned to each party regarding a project site. It typically details which party is responsible for aspects such as site access, security, maintenance, and compliance with safety regulations. For example, the schedule may specify that the contractor is responsible for site cleanliness while the owner handles utility connections. This clause ensures clear allocation of responsibilities, reducing the risk of disputes and misunderstandings during the course of the project.
POPULAR SAMPLE Copied 1 times
Site Responsibility Schedule. A Site Responsibility Schedule (SRS) for every connection point shall be prepared by the owner of the sub-station where connection is taking place. The details shall be provided as annexure (Annexure-1) to the agreement. The site responsibility schedule shall be prepared by TS TRANSCO/ TS DISCOM (whichever is applicable) and the user, detailing the ownership responsibilities of each, before execution of the project or connection, including safety responsibilities. The following information shall be included in Site Responsibility Schedule (SRS), namely: a) Schedule of electrical apparatus, services, and supplies. b) Schedule of telecommunications and measurement apparatus c) Safety rules applicable to each plant/apparatus. d) The ownership of Plant/apparatus e) The responsibility for control of Plant/apparatus f) The responsibility for maintenance of plant /apparatus g) The responsibility for operation of plant/apparatus h) The manager of the site i) The responsibility for all matters relating to safety of persons at site j) The responsibility for all matters relating to safety of equipment at site No connection shall be made unless Site Responsibility Schedule is prepared and signed by all concerned parties.
Site Responsibility Schedule. 1.3.1 As soon as reasonably practicable a document shall be prepared by the Company (reflecting the details agreed between the Company and the Customer) in respect of the site pursuant to the Agreement and signed by both Parties by way of confirmation of its accuracy, detailing the division of responsibilities at the interface site in respect of ownership, control, operation, maintenance and safety (“the Site Responsibility Schedule”). The Customer shall provide to the Company upon request all such information as is required by the Company to enable it to prepare the Site Responsibility Schedule prior to the commencement of permanent and/or temporary works required for the design, construction, completion and commissioning of the Facility and Contestable Components. 1.3.2 An ownership diagram shall be included in the Site Responsibility Schedule incorporating numbering, nomenclature and labelling. Apparatus to be shown and the preferred graphical symbols to be used shall be in accordance with the Company’s standard practice. 1.3.3 A copy of the Site Responsibility Schedule including the ownership diagram shall be retained by the Company and by the Customer. 1.3.4 The Customer shall notify the Company of any changes at or relating to the site which may affect the Site Responsibility Schedule or ownership diagram and the Company shall carry out any necessary updating and the principles set out in Paragraph 1.3.1 shall apply to such updating. 1.3.5 The Site Responsibility Schedule shall detail the demarcation of the responsibility for safety of persons carrying out work or testing at the site on circuits which cross the site at any point.
Site Responsibility Schedule. (1) A site Responsibility Schedule (SRS) for every connection point shall be prepared by the generating company or licensee operating the electricity system to which connection is taking place. (2) Following information shall be included in the Site Responsibility Schedule, namely,- (a) Schedule of electrical apparatus services and supplies; (b) Schedule of telecommunications and measurement apparatus; and (c) Safety rules applicable to each plant and apparatus. (3) Following information shall also be furnished in the Site Responsibility Schedule for each item of equipment installed at the connection site, namely: - (a) The ownership of equipment; (b) The responsibility for control of equipment; (c) The responsibility for maintenance of equipment; (d) The responsibility of operation of equipment; (e) The manager of the site; (f) The responsibility for all matters relating to safety of persons at site; and (g) The responsibility for all matter relating to safety of equipment at site.
Site Responsibility Schedule. In order to inform site operational staff and NEPCO control engineers of agreed responsibilities for Plant and/or Apparatus at the operational interface, a Site Responsibility Schedule shall be produced for NEPCO and the “User” with whom they interface in accordance with the Connection Conditions of the Grid Code. Company: Power Station name:
Site Responsibility Schedule. The site responsibility schedule, as per the Orissa Grid Code (OGC) (Appendix to Chapter-5) is annexed as Annexure - III.
Site Responsibility Schedule. Not later than eight (8) weeks prior to the expected commencement date of the Commissioning Programme or by such other time as may be agreed between the Parties each Party shall submit to the other: a) for the Connection Site, information to enable preparation of Site Responsibility Schedules complying with the provisions of the Grid Code together with a list of managers who have been duly authorised by the “User” to sign such Site Responsibility Schedules on behalf of the “User”; b) written confirmation that the list of safety co-ordinators are authorised and competent in accordance with the conditions in the operation code of the Grid Code; c) a list of the telephone numbers for the facsimile machines referred to in the connection code of the Grid Code.