Common use of Shifting of obstructing utilities Clause in Contracts

Shifting of obstructing utilities. The contractor shall, subject to applicable laws and with assistance to Authority, undertaking shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway in accordance with this agreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. The authority will provide assistance to the contractor for obtaining the estimates for shifting of such utilities from entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Engineer (AE) in accordance with the provision of agreement. The supervision charge only shall be paid by the Authority to the Utility owning entity. In the event of delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility to be shifted dismantled shall belong to the contractor who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3

Appears in 8 contracts

Samples: Draft Contract Agreement, nhidcl.com, Draft Contract Agreement

AutoNDA by SimpleDocs

Shifting of obstructing utilities. The contractor Contractor shall, subject to applicable laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric linesline, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway Highway in accordance with this agreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting Shifting utilities not included in the Schedule B, B if any, any shall be treated as Change of Scope. The authority Authority will provide assistance to the contractor Contractor for obtaining the estimates for shifting of such utilities from entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Engineer (AE) in accordance with the provision of agreement. The supervision charge only shall be paid by the Authority to the Utility owning entity. In the event of delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The Contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority Engineer (AE) in accordance with the provision of agreement. The supervision charges only shall be paid by the authority to the Utility owning entity. In the event of any delay in shifting thereof the contractor shall be responsible for failure to perform any of its obligation here under if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables as the case may be. The dismantled material/scrap of existing utility Utility to be shifted shifting dismantled shall belong to the contractor Contractor who would be free to dispose-off the dismantled material materials as deemed fit by them. them The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 6 contracts

Samples: Draft Contract Agreement, Contract Agreement, Draft Contract Agreement

Shifting of obstructing utilities. The contractor shall, subject to applicable laws and with assistance to Authority, undertaking shifting of any utility (including removal of trees or shifting, electric lines, water pipes and telephone cables, sewer line over or underground or other structure etc.), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway in accordance with this agreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule B, if any, shall not be treated as Change of Scope. The authority will provide assistance to the contractor for obtaining the estimates for shifting of such utilities from entity owning such electric lines, water pipes or telephone cables, tress, sewer lines etc., as the case may be. The contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Engineer (AE) in accordance with the provision of agreement. The supervision charge only shall be paid by the Authority to the Utility owning entity. In the event of delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility to be shifted dismantled shall belong to the contractor who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 3 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

Shifting of obstructing utilities. The contractor shall, subject to applicable laws and with assistance to Authority, undertaking shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway in accordance with this agreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. The authority will provide assistance to the contractor for obtaining the estimates for shifting of such utilities from entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Engineer (AE) in accordance with the provision of agreement. The supervision charge only shall be paid by the Authority to the Utility owning entity. In the event of delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility to be shifted dismantled shall belong to the contractor who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 3 contracts

Samples: Contract Agreement, Contract Agreement, Draft Contract Agreement

Shifting of obstructing utilities. 11.2.1 The contractor Concessionaire shall, subject to applicable laws Applicable Laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected affects the execution of works Works or maintenance of the project highway Project Highway in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such such, utilities indicated in Schedule Schedule-B is payable to the Contractor Concessionaire as per Schedule H. part of Bid Project Cost. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. The authority Authority will provide assistance to the contractor Concessionaire for obtaining the estimates for shifting of such utilities from the entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor Concessionaire shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Independent Engineer (AEIE) in accordance with the provision of agreementAgreement. The supervision charge charges only shall be paid by the Authority to the Utility owning entityOwning Entity. In the event of any delay in shifting thereof, the Contractor Concessionaire shall be responsible for failure to perform any of its obligations here under hereunder if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/material/ scrap of existing utility Utility to be shifted shifted/ dismantled shall belong to the contractor Concessionaire who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor Concessionaire any time after signing of the Agreement. 9.3.

Appears in 2 contracts

Samples: Draft Concession Agreement, Concession Agreement

Shifting of obstructing utilities. The contractor Concessionaire shall, subject to applicable laws Applicable Laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected affects the execution of works Works or maintenance Maintenance of the project highway Project Highway in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule Schedule-B, if any, shall be treated as Change of Scope. The authority Authority will provide assistance to the contractor Concessionaire for obtaining the estimates for shifting of such utilities from the entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor Concessionaire shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Independent Engineer (AEIE) in accordance with the provision of agreement. The supervision charge charges only shall be paid by the Authority to the Utility utility owning entity. In the event of any delay in shifting thereof, the Contractor Concessionaire shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility Utility to be shifted shifted/dismantled shall belong to the contractor Concessionaire who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor Concessionaire any time after signing of the Agreement. 9.3.

Appears in 2 contracts

Samples: Model Concession Agreement, Model Concession Agreement

Shifting of obstructing utilities. 11.2.1 The contractor Concessionaire shall, subject to applicable laws Applicable Laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected affects the execution of works Works or maintenance of the project highway Project Highway in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such such, utilities indicated in Schedule Schedule-B is payable to the Contractor Concessionaire as per Schedule H. part of Bid Project Cost. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. .. The authority Authority will provide assistance to the contractor Concessionaire for obtaining the estimates for shifting of such utilities from the entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor Concessionaire shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Independent Engineer (AEIE) in accordance with the provision of agreementAgreement. The supervision charge charges only shall be paid by the Authority to the Utility owning entityOwning Entity. In the event of any delay in shifting thereof, the Contractor Concessionaire shall be responsible for failure to perform any of its obligations here under hereunder if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/material/ scrap of existing utility Utility to be shifted shifted/ dismantled shall belong to the contractor Concessionaire who would be free to dispose-off the dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor Concessionaire any time after signing of the Agreement. 9.3.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Shifting of obstructing utilities. The contractor shall, subject to in accordance with applicable laws and with the assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected affects the execution of works Works or maintenance Maintenance of the project highway Project Highway in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such such, utilities indicated in Schedule Schedule-B is payable to the Contractor as per Schedule indicated in Schedule-H. Cost All over ground utilities including electrical/power/water utilities shall be responsibility of shifting the Contractor, whether indicted in Schedule-B or not. No Change of Scope (CoS) shall be allowed for such over ground utilities whether indicated in Schedule-B or not. However, underground utilities as indicated in Schedule-B will only be considered as part of scope of work. Underground utilities, if any, not included in the Schedule B, if any, Schedule-B shall be treated as Change of Scope. The authority will provide assistance Contractor shall prepare detailed proposal for utility diversion alongwith specifications for submission to the contractor for obtaining utility owning agency and submit with recommendation of the estimates for shifting of such utilities from entity owning such electric lines, water pipes or telephone cables, as the case may beAuthority. The contractor Contractor shall also prepare as executed drawings and get the acceptance of concerned utility owning department for release of payment. The Contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s 's Engineer (AE) in accordance with the provision of agreement. The supervision charge charges only shall be paid by the Authority to the Utility owning entityOwning Entity, if any. In the event of any delay in shifting thereof, the Contractor contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on part of the entity owning such electric lines, water pipes or telephone cables, as the case may beunder. The dismantled material/material / scrap of existing utility Utility to be shifted / dismantled shall belong to the contractor Contractor/Concessionaire who would be free to dispose-off the dismantled Dismantled material as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 1 contract

Samples: Draft Contract Agreement

Shifting of obstructing utilities. The contractor shall, subject to applicable laws Applicable Laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway Highway in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance with applicable standards and specifications of concerned utility owning entity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. The authority Authority will provide assistance to the contractor Contractor for obtaining to the estimates Contractor for shifting of obtaining such utilities from the entity owning such electric lines, water pipes or telephone cables, as the case may be. The contractor Contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Authority Engineer (AE) in accordance with the provision of agreement. The supervision charge charges only shall be paid by the Authority to the Utility owning entityOwning Entity. In the event of any delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility Utility to be shifted dismantled shall belong to the contractor Contractor who would be free to dispose-off the dismantled material materials as deemed fit by them. The work of shifting of utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 1 contract

Samples: nhidcl.com

Shifting of obstructing utilities. The contractor shall, subject to applicable laws and with assistance to of the Authority, undertaking undertake shifting of any utility (including electric lines, water pipes and telephone cables), to an appropriate location or alignment, if such utility or obstruction adversely affected the execution of works or maintenance of the project highway Site in accordance with this agreementAgreement, as per the scope given in Schedule B and in accordance inaccordance with applicable standards and specifications of concerned utility owning entityowningentity. The cost of such utility shifting of such utilities indicated in Schedule B is payable to the Contractor as per Schedule H. Cost of shifting utilities not included in the Schedule B, if any, shall be treated as Change of Scope. The authority Authority will provide assistance to the contractor tothe Contractor for obtaining the estimates for shifting of such utilities from entity owning the entityowning such electric lines, water pipes or telephone cables, as the case may be. The contractor Contractor shall execute such utility shifting works under the supervision of utility owning agency and Authority’s Authority Engineer (AE) in accordance with the provision of agreement. The supervision charge charges only shall be paid by the Authority to the Utility owning entityutility Owning Entity. In the event of any delay in shifting thereof, the Contractor shall be responsible for failure to perform any of its obligations here under if such failure is not as a direct consequence of delay on the part of the entity owning such electric lines, water pipes or telephone cables, as the case may be. The dismantled material/scrap of existing utility to be shifted dismantled shall belong to the contractor Contractor who would be free to dispose-off the dismantled material materials as deemed fit by them. The work of shifting of utilities Utilities can be taken up by the Contractor any time after signing of the Agreement. 9.3.

Appears in 1 contract

Samples: nhidcl.com