Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works. 48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected. 48.3 On completion of the whole works, the contractor may substitute retention money with an “on demand” Bank guarantee.
Appears in 36 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor Contractor may substitute retention money with an “on demand” Bank guarantee.
Appears in 7 contracts
Sources: Bidding Agreement, Civil Works Agreement, Project Agreement
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money (balance half) with an “on demand” Bank guarantee.
Appears in 4 contracts
Sources: Construction Contract, Construction Contract, Construction Contract
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor Contractor may substitute retention money (balance half) with an “on demand” Bank guarantee.
Appears in 3 contracts
Sources: Project Agreement, Invitation for Bid (Ifb), Procurement Agreement
Retention. 48.1 48.1. The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 48.2. On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 48.3. On completion of the whole works, the contractor may substitute retention money with an “on demand” Bank guarantee.
Appears in 3 contracts
Sources: Bidding Document, Construction Contract, Bid Document
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money money(balance half) with an “on demand” Bank guarantee.
Appears in 3 contracts
Sources: Punjab Rural Water Supply & Sanitation Project Agreement, Construction Agreement, Punjab Rural Water Supply & Sanitation Project Agreement
Retention. 48.1 The Employer employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion completion of the whole of the Works works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money with an “on demand” Bank guaranteeGuarantee.
Appears in 2 contracts
Sources: Tender Agreement, Construction Contract
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.the
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, under capital cost indicated in the Activity Schedule the contractor may substitute retention money (balance half) with an “on demand” Bank guarantee.
Appears in 1 contract
Sources: Construction Contract
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money (balance half) with an “on demand” Bank guarantee. ▇▇▇.▇▇/W-2
Appears in 1 contract
Sources: Punjab Rural Water Supply & Sanitation Project Agreement
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 48.2. On Completion of the whole of the Works works half the total amount retained is repaid to the Contractor contractor and half when the Defects Liability Period defects liability period has passed and the Engineer has certified that all Defects defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 48.3. On completion of the whole works, the contractor may substitute retention money with an “"on demand” " Bank guarantee.
Appears in 1 contract
Sources: Procurement Agreement
Retention. 48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money (balance half) with an “on demand” ―on demand‖ Bank guarantee.
Appears in 1 contract
Sources: Construction Contract
Retention. 48.1 Deleted
48.2.1 Deleted
48.3 Deleted
48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and half when the Defects Liability after contract Period has passed and the Engineer has certified that all Defects notified by the Engineer to the Contractor before the end works completed as per specification of this period have been correctedcontract document.
48.3 On completion of the whole works, the contractor may substitute retention money with an “"on demand” " Bank guarantee.
Appears in 1 contract
Sources: Construction Agreement