Relief Event. In the event that there shall be a Relief Event and a Party claiming the Relief Event uses commercially reasonable efforts to mitigate the consequences of any time delay resulting therefrom (including, where possible, establishing a contingency plan on commercially reasonable terms which will allow such Party’s normal operations to be resumed within a reasonable time thereafter) and shall have provided Notice to either of the Owner or the Project Manager, as the case may be, with respect to the occurrence of the Relief Event within seven (7) days of its occurrence, the Project Manager or the Owner, as the case may be, shall be entitled to an extension of time with respect to the obligations of the Project Manager or the Owner, as the case may be, directly and adversely affected by the Relief Event equal to the time during which the Relief Event occurred.

Appears in 2 contracts

Sources: Project Management Agreement, Project Management Agreement