Rejected Work. 23.1 If Owner or ▇▇▇▇▇ rejects or orders to be removed and replaced any of Subcontractor's Work which Owner or ▇▇▇▇▇ determines does not comply with the requirements of this Agreement or the Contract Documents, Subcontractor, within forty-eight (48) hours after receipt of such notice, shall proceed to take down the rejected work, remove the rejected materials from the Construction Site, repair (or pay the cost of repairing) damage to the work of others caused thereby, and replace the same with work and materials complying with the requirements of the Contract Documents. If Subcontractor does not commence such replacement work promptly or does not diligently complete such removal and replacement, ▇▇▇▇▇ by written notice may immediately take over the completion of such removal and replacement, and in such event Subcontractor shall repay ▇▇▇▇▇ its costs, plus 10% for ▇▇▇▇▇’ overhead and other indirect expenses, upon demand.