Common use of Reassessment Clause in Contracts

Reassessment. If Reassessment of the System Impact Study is required due to a higher queued project dropping out of the queue, a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.1, IPA shall notify Interconnection Customer in writing. IPA, or a consultant approved by IPA, shall use Reasonable Efforts to complete such reassessment within sixty (60) calendar days from the date of notice, subject to extension in the manner specified in Section 7.3. All costs of associated with a reassessment shall be borne by Interconnection Customer.

Appears in 3 contracts

Samples: Intermountain Power Agency, Intermountain Power Agency, Intermountain Power Agency

AutoNDA by SimpleDocs

Reassessment. β€Œ If Reassessment of the System Impact Study is required due to a higher queued project dropping out of the queue, a modification of a higher queued project subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 7.1, IPA shall notify Interconnection Customer in writing. IPA, or a consultant approved by IPA, shall use Reasonable Efforts to complete such reassessment within sixty (60) calendar days from the date of notice, subject to extension in the manner specified in Section 7.3. All costs of associated with a reassessment shall be borne by Interconnection Customer.

Appears in 2 contracts

Samples: Intermountain Power Agency, Intermountain Power Agency

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.